Resolved that – (i) a contractual arrangement be negotiated with Jarvis to allow for a capital investment fund to be set up in the region of £10.8m in order for the scheme to proceed; (ii) a minimum of provision of 210 beds be guaranteed by the operator for Liverpool school children during each school term with 25% off the charges for Liverpool schools, rising to 50% off for Liverpool school children entitled to free school meals; (iii) subject to affordability, existing capacity of 523 beds be maintained; and (iv) to allow the scheme to proceed, approval be given to engage design and other consultants for the capital works and New Opportunities Fund works together with the serving of notices on affected leaseholders and the submission of all necessary planning applications.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
CITY STATUS – PUBLIC LL/20 Portfolios: Education and Lifelong Executive Members: Learning / Resources Cllr Paul Clein / Cllr Chris Curry Date of submission: Subject: Colomendy Outdoor Centre 10 / 15 October 2003 for Education - Redevelopment Report No. DE/102/03 Contact officer: Ken McCandless Background papers: Ext: 233 8222 DE/175/01 – Executive Board, 19 October 2001 Outline Development Proposals – December 2001 Application to New Opportunities Fund – March 2002 A Viable Future – May 2002 DE/90/02. DE/013/03. DE/025/03 Executive summary: The purpose of this report is to advise members on the current situation with regard to the proposed redevelopment of the Colomendy Centre for Outdoor Education and to obtain authority to enable the scheme to progress.
The Authority were informed by the DfES in late March that a second application for PFI funding for the project was not successful – apparently only 1 in 6 applications succeeded. Prior to the PFI application being submitted, an advertisement had been placed in the official journal of the European Community (OJEC) inviting Expressions of Interest from potential private partners wishing to work with the Authority in developing long term proposals for the modernisation of Colomendy. As a result of this process, Jarvis are now the Authority’s preferred service provider for Colomendy.
A series of meetings have taken place recently with Jarvis and an ‘Action Plan’ presented to the Colomendy Management Committee on 23 July 2003 will provide the basis for a costed business plan. Fundamental to any redevelopment at Colomendy is capital investment, estimated to be in the region of £10.8m.
To date, funding identified is as follows:-
a) Stage 1 approval to an application to the New Opportunities Fund for outdoor adventure facilities in the sum of £780,000. b) Executive Board (October 2001) approval to an operating subsidy of up to £500,000 per annum if necessary. (Jarvis and the Authority are currently in discussions with a major operator of outdoor education facilities who believe that given the right circumstances, Colomendy could be turned around to a profit making concern without an operating subsidy from the Council). Key to any successful operation of Colomendy would be:-
a) Upgraded accommodation necessitating capital expenditure in the region of £10.8m. b) A guarantee by the operator of a minimum provision of 210 beds for Liverpool school children during each school term at similar discount levels to charges that are currently being offered to Liverpool school children. i.e. 25% off the charges for Liverpool schools, rising to 50% off for Liverpool school children entitled to free school meals. c) To enable an operator to take on the demand risk and market the Centre to a wider and larger potential user group, it is important to maintain existing capacity levels of 523 beds, subject of course to affordability.
In order to allow the scheme to progress, Jarvis have proposed that they set up a capital investment fund in the region of £10.8m with the Authority paying a Unitary Charge to Jarvis over the anticipated 30 year contract period. The Unitary Charge is estimated to be equivalent to the current level of revenue funding i.e. approximately £1m after adjustment for asset charges. This sum includes the £500,000 operating subsidy aforementioned.
The Stage 2 application for the NOF Funding needs to be submitted by 31 March 2004 but in order to maintain the overall timetable for completion in April 2005, the engagement of design and other consultants for both the capital and NOF works together with the serving of notices on affected leaseholders and the submission of all necessary planning applications needs to proceed now.
Executive Director recommendation: Colin Hilton recommends that –
a) a contractual arrangement be negotiated with Jarvis to allow for a capital investment fund to be set up in the region of £10.8m in order for the scheme to proceed;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.