Redevelopment of Colomendy Centre for Outdoor Education (CHS/12)

Approved Committee 1 paper

Children's Services Select Committee 2005/2006 approved this item on Thursday 29 September 2005. Below is the council's own wording, with the papers it was decided on.

Item34

Resolved

Resolved that – the recommendation be approved; and the decision be referred to the Children’s Services Select Committee.” _____ The Select Committee was asked to note that since referral of this decision by the Executive Board the item had been called in for scrutiny as follows – Councillors Jane Corbett, Steve Munby, Violet Bebb, Alan Walker and Joe Anderson To scrutinise the accuracy of the information; the arrangements and relationship with the proposed developer; the impact upon Liverpool children; the financial implications and the option appraisal. _____ With the permission of the Committee Bishop James addressed the meeting on this matter. A memorandum submitted by the Bishop to outline a proposal seeking the formation of a Colomendy Anniversary Trust to take the redevelopment initiative forward had been circulated to members of the Committee. Issues: seeking formation of a shadow trust of beneficiaries and trustees commissioning of design team to review the site to assess planning permissions in place to draw up a sustainable business plan and seek charitable status to initiate applications for public and private funding to enter in to a leasing agreement containing reversionary clauses with the City Council to launch a Colomendy anniversary trust _____ Members of the Committee: Councillor Firth questioned controls over private sector costs, likely fee structures between LCC and the Bishop’s proposal along with levels of subsidy. Colin Hilton responded on the principles of pricing and contract provisions indicating the preferred developer needed to demonstrate income levels pre-contract. Ann Melville outlined figures from consultants in terms of seasonal rates at Colomendy Chair questioned the timescale for ... view the full minutes text for item 34.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Children's Services Select Committee 2005/2006, 8 pages

CITY STATUS – PUBLIC CHS/12 Portfolios: Executive Members: Children’s Services / Resources Cllr Paul Clein / Cllr Keith Turner

Date of submission: Subject: Redevelopment of 15 / 17 August 2005 Colomendy Centre for Outdoor Education Report No. DE/07/05 Contact officer: Ken McCandless Background papers: DE/102/03, Ext: 233 8222 DE/53/04 Colomendy Hall Development Study.

Executive summary: The purpose of this report is to:

a) Update Members on the current situation with regard to the proposed redevelopment of the Colomendy Centre for Outdoor Education b) Confirm a commitment to carry out a major redevelopment of the site at an estimated cost of £10.1 million (at December 2006 price base) subject to corporate considerations over the level of borrowing for capital purposes and its effect on the Capital Programme and Council Tax and subject to the following conditions: i) that Kingswood produce a satisfactory business plan for the future development of the centre. ii) that Kingswood achieve the targets set out in the proposed three- year Initial Services Phase Agreement iii) that the Schools Forum agrees to top-slice the Schools Budget by £500,000 to provide for the revenue contribution. (The schools, as part of the agreement with Kingswood will receive subsidised places for all Liverpool children and enhanced subsidy for those children who are from families on low income and this will continue in the enhanced provision.) c) Subject to the above commitment to approve the seeking of tenders now for new and improved outdoor adventure facilities at an estimated cost of £1,060,000 (at current prices) financed by a £780,000 NOF lottery grant that has been approved for this purpose and must be spent by 31 March 2006, and a Council contribution of £280,000 from the earmarked reserve for the Colomendy centre. d) Subject to the above to enter an Initial Services Phase Agreement with the preferred operator (Kingswood) for them to operate the Centre and for them to carry out sufficient minor redecoration and refurbishment using their own funds to enable continued use of the Centre until such time as the full refurbishment is carried out. Members may recall from previous reports about the Colomendy Centre that the buildings on the site are in extremely poor state of repair and decoration, require new furnishings and do not meet the needs of current customers. As a result of this, together with continued speculation about a major refurbishment scheme, the Centre now attracts very few customers. The Centre currently makes a deficit in the region of £1 million per year even though staffing has already been reduced significantly.

To date no contracts have been signed nor has any redevelopment works begun. However, substantial progress has been made both in terms of design development and also operational planning. In taking the project forward the design team has worked closely with the preferred operator, Kingswood, and the local Planning Authority.

In terms of design development, the current situation is: a) All planning permissions for the major redevelopment and the outdoor adventure facilities are now in place. b) Planning conditions necessary before any works begin are being actioned (e.g. licenses in connection with any proposed working that could affect great crested newts, lesser horseshoe bats and badgers that currently occupy the site). c) An Environmental Impact Assessment has been undertaken and provided to the planning authority. d) An application has been made to obtain a public footpath diversion order for which planning permission has already been obtained. e) A design freeze is in place.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Redevelopment of Colomendy Centre for Outdoor Education (CHS/12)Report 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

19 of 29 attended
GC
Gerry CallaghanOfficer, expected
MG
Margaret GillOfficer, present
MF
Matt FinneganOfficer, expected
KA
Councillor Karen AffordMember, present
MA
Councillor Mohamed AliMember, present
EA
Councillor Elaine AllenMember, present
PA
Councillor Peter AllenAlternate, present
VB
Councillor Violet BebbMember, present
VB
Councillor Vera BestMember, present
JC
Councillor Jeremy ChowingsMember, expected
JC
Councillor John ClucasMember, present
JC
Councillor Jane CorbettMember, present

All 29 on the meeting page

On this subject at Liverpool

Search all
  1. Redevelopment of Colomendy Centre for Outdoor Education (CHS/12)This decision
  2. Redevelopment of Colomendy Centre for Outdoor Education (CH/12)Noted
  3. Colomendy Outdoor Centre for Education - RedevelopmentApproved

More from Liverpool Children's Services Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
13 Apr 2006 BME Educational AttainmentAgreed to approve the proposed review as outlined in the report. Agreed Open
13 Apr 2006 Result of consultations on a proposal to discontinue Garston CE Primary School (CHS/49)Resolved that – (i) the recommendation be approved; and (ii) the decision be referred to the Children’s Services Sele... Approved Open
13 Apr 2006 Admission Policy for Community and Controlled Church of England Primary Schools for September 2007Agreed that the content of the report and the proposed admission policy for Community and Controlled Church of Englan... Agreed Open
13 Apr 2006 Admission Policy for Community Secondary Schools for September 2007Agreed that the content of the report and the proposed admission policy for Community Secondary Schools for September... Agreed Open
13 Apr 2006 Scheme of DelegationAgreed that the report be noted. Further discussion took place around allocation of Youth Service budget to Neighbour... Agreed Open