Redevelopment of Colomendy Centre for Outdoor Education (CHS/12)
ApprovedCommittee1 paper
Children's Services Select Committee 2005/2006 approved this item on Thursday 29 September 2005. Below is the council's own wording, with the papers it was decided on.
Resolved that – the recommendation be approved; and the decision be referred to the Children’s Services Select Committee.” _____ The Select Committee was asked to note that since referral of this decision by the Executive Board the item had been called in for scrutiny as follows – Councillors Jane Corbett, Steve Munby, Violet Bebb, Alan Walker and Joe Anderson To scrutinise the accuracy of the information; the arrangements and relationship with the proposed developer; the impact upon Liverpool children; the financial implications and the option appraisal. _____ With the permission of the Committee Bishop James addressed the meeting on this matter. A memorandum submitted by the Bishop to outline a proposal seeking the formation of a Colomendy Anniversary Trust to take the redevelopment initiative forward had been circulated to members of the Committee. Issues: seeking formation of a shadow trust of beneficiaries and trustees commissioning of design team to review the site to assess planning permissions in place to draw up a sustainable business plan and seek charitable status to initiate applications for public and private funding to enter in to a leasing agreement containing reversionary clauses with the City Council to launch a Colomendy anniversary trust _____ Members of the Committee: Councillor Firth questioned controls over private sector costs, likely fee structures between LCC and the Bishop’s proposal along with levels of subsidy. Colin Hilton responded on the principles of pricing and contract provisions indicating the preferred developer needed to demonstrate income levels pre-contract. Ann Melville outlined figures from consultants in terms of seasonal rates at Colomendy Chair questioned the timescale for ... view the full minutes text for item 34.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Children's Services Select Committee 2005/2006, 8 pages
CITY STATUS – PUBLIC CHS/12 Portfolios: Executive Members: Children’s Services / Resources Cllr Paul Clein / Cllr Keith Turner
Date of submission: Subject: Redevelopment of 15 / 17 August 2005 Colomendy Centre for Outdoor Education Report No. DE/07/05 Contact officer: Ken McCandless Background papers: DE/102/03, Ext: 233 8222 DE/53/04 Colomendy Hall Development Study.
Executive summary: The purpose of this report is to:
a) Update Members on the current situation with regard to the proposed redevelopment of the Colomendy Centre for Outdoor Education b) Confirm a commitment to carry out a major redevelopment of the site at an estimated cost of £10.1 million (at December 2006 price base) subject to corporate considerations over the level of borrowing for capital purposes and its effect on the Capital Programme and Council Tax and subject to the following conditions: i) that Kingswood produce a satisfactory business plan for the future development of the centre. ii) that Kingswood achieve the targets set out in the proposed three- year Initial Services Phase Agreement iii) that the Schools Forum agrees to top-slice the Schools Budget by £500,000 to provide for the revenue contribution. (The schools, as part of the agreement with Kingswood will receive subsidised places for all Liverpool children and enhanced subsidy for those children who are from families on low income and this will continue in the enhanced provision.) c) Subject to the above commitment to approve the seeking of tenders now for new and improved outdoor adventure facilities at an estimated cost of £1,060,000 (at current prices) financed by a £780,000 NOF lottery grant that has been approved for this purpose and must be spent by 31 March 2006, and a Council contribution of £280,000 from the earmarked reserve for the Colomendy centre. d) Subject to the above to enter an Initial Services Phase Agreement with the preferred operator (Kingswood) for them to operate the Centre and for them to carry out sufficient minor redecoration and refurbishment using their own funds to enable continued use of the Centre until such time as the full refurbishment is carried out. Members may recall from previous reports about the Colomendy Centre that the buildings on the site are in extremely poor state of repair and decoration, require new furnishings and do not meet the needs of current customers. As a result of this, together with continued speculation about a major refurbishment scheme, the Centre now attracts very few customers. The Centre currently makes a deficit in the region of £1 million per year even though staffing has already been reduced significantly.
To date no contracts have been signed nor has any redevelopment works begun. However, substantial progress has been made both in terms of design development and also operational planning. In taking the project forward the design team has worked closely with the preferred operator, Kingswood, and the local Planning Authority.
In terms of design development, the current situation is: a) All planning permissions for the major redevelopment and the outdoor adventure facilities are now in place. b) Planning conditions necessary before any works begin are being actioned (e.g. licenses in connection with any proposed working that could affect great crested newts, lesser horseshoe bats and badgers that currently occupy the site). c) An Environmental Impact Assessment has been undertaken and provided to the planning authority. d) An application has been made to obtain a public footpath diversion order for which planning permission has already been obtained. e) A design freeze is in place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Children's Services Select Committee 2005/2006 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.