Resolved that – (i) the recommendation of the Project Jennifer Evaluation Panel to select St. Modwen Developments Ltd. as their preferred developer partner to deliver a new district centre at Scotland Road/Great Homer Street, be endorsed; (ii) Officers be authorised to negotiate detailed terms with St. Modwen Developments Ltd. for a development agreement in respect of this proposal; (iii) St. Modwen Developments Ltd. be invited to prepare a detailed Masterplan for the creation of a new district centre at Scotland Road/Great Homer Street in consultation with Council members, Officers, other public agencies, the local community and businesses that will be affected by the proposals; and (iv) the completed Masterplan and a summary of the negotiated detailed terms be reported back to the Executive Board for approval in due course.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1.1The Executive Board of 25th April 2003 authorised officers to market the opportunity to develop a new district centre at Scotland Road/Great Homer Street on the site of the Taylor Street Industrial Estate.
1.2Interested parties were invited to complete a pre-qualification questionnaire (PQQ) and return it by 11th June 2003.
1.3The PQQs received by the closing date were evaluated and scored by a multi-disciplinary team of Officers. Having considered the scores which resulted the Executive Board of 19th September 2003 approved the short-listing of the following companies:
David McLean Developments Ltd. Maro Developments Ltd. Neptune Developments Ltd. St. Modwen Developments Ltd. Tesco Stores Ltd.
1.4Tender documents were sent to the five short-listed bidders with a closing date for the return of bids of 12th November 2003. 2. Technical Evaluation Process
2.1Bids were received from all five short-listed bidders.
2.2They were evaluated by a multi-disciplinary team of officers. The marks in respect of some areas of the technical evaluation were weighted as being more important than others.
2.3The result of this exercise was that the bidder with the highest score was St. Modwen Developments Ltd.
3. Community Forum
3.1An exhibition of the five proposals was held for the Community Forum in the new visitor centre at the rear of St. Anthony’s Church, Scotland Road on 28th November.
3.2The overall outcome was that St. Modwen emerged as the most popular scheme.
4. Evaluation Panel
4.1The Panel met on 10th December 2003 and received presentations from each of the five short-listed bidders.
4.2Following each presentation the Panel members asked the bidders probing questions on their proposals and their ability to deliver them.
4.3Having considered the presentations, the answers to the questions, the technical appraisal, and the outcome of the Community Forum meeting, the Panel decided to select St. Modwen Developments Ltd. as their preferred developer partner.
5. Next Steps
5.1If the nomination of St. Modwen Developments Ltd. is endorsed by the Executive Board they will be required to prepare a master-plan for the development of the site and to negotiate with the City Council terms for the development agreement which will control its delivery.
5.2The master-plan and the detailed heads of terms for the development agreement will be reported back to the Executive Board for approval.
Executive Member/Director recommendation Councillors Peter Millea and Chris Curry/Charlie Parker.
That:
(i) the recommendation of the Project Jennifer Evaluation Panel to select St. Modwen Developments Ltd. as their preferred developer partner to deliver a new district centre at Scotland Road/Great Homer Street be endorsed;
(ii) Officers be authorised to negotiate detailed terms with St. Modwen Developments Ltd. for a development agreement in respect of this proposal;
(iii) St. Modwen Developments Ltd. be invited to prepare a detailed Masterplan for the creation of a new district centre at Scotland Road/Great Homer Street in consultation with Council members, Officers, other public agencies, the local community and businesses that will be affected by the proposals; and
(iv) the completed Masterplan and a summary of the negotiated detailed terms be reported back to the Executive Board for approval in due course
Key Decision
Yes
Forward Plan
Yes
Implementation effective from
13 February 2004
Timescale for action
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.