Resolved that – (i) the City Council’s capital programme be adjusted to reflect increased expenditure in this financial year of £137,000; (ii) authority be granted for the Executive Director (Regeneration) to accept a Mersey Waterfront Regional Park grant approval in the sum of £ 68,500 for the financial year 2003/2004. The City Council will thereby agree to act as accountable body for the Mersey Waterfront Regional Park grant with the Divisional Manager (Regeneration Initiatives) taking the lead responsibility in ensuring the duties of the accountable body are administered appropriately. (iii) the City Council agrees to the Northwest Development Agency’s proposal of a retrospective approval of grant in the sum of £68,500; and (iv) authority be granted for the Executive Director (Regeneration) to commit expenditure to procure the further development of the Cruise Liner facility in terms of detailed design and site investigation.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1.1Members of the Board will be aware of the Cruise Liner facility proposal which is a strategic project within the City Centre IDP, the Pier Head Masterplan and the Mersey Waterfront Regional Park Commencement Plan. The project aims to provide a world class facility at Princes Dock to enable the efficient and sustainable berthing of large cruise, naval and other vessels (e.g. Tall Ships).
1.2Members of the Board may also recall the description of the market gap which the project is seeking to fill. This market gap relates to the projected income from the facility which - whilst being capable of covering cost at Year 4 of operation - is insufficient to justify the capital investment from a commercial perspective.
1.3Principally for this reason, grant funding is required to deliver the physical facility in respect of which European Commission state aid rules and competition rules:
• Prohibit Mersey Docks and Harbour Company (MDHC) from obtaining grant to deliver a Cruise Liner facility. This has been tested previously by MDHC;
• Require the City Council to act as accountable body and ‘beneficiary’ of the project – owning and receiving the income generated by the facility.
1.4Previously, the Board has given authority to accept Stage 1 grant funding totalling £260,000 provided on a 50:50 basis by the Northwest Development Agency and by City Focus SRB 6. A sum of £176,948 has been expended last financial year – the balance of £83,052 has been committed and will be defrayed this financial year.
1.5These funds have enabled the preparation of:
• Designs and costs; • An environmental impact assessment; • An updated business plan and cash flow projections; • Applications for consent under the Town & Country Planning Act (Planning Permission, Conservation Area Consent and a Stopping Up Order) as well as under the Harbour Works Act (Harbour Revision Order/HRO).
1.6The latter applications have been submitted by MDHC and the works contract has also been advertised in the OJEC with six contractor consortia being short-listed. The completion of these tasks has also enabled detailed funding applications to be submitted to the NWDA, City Focus SRB, Objective One and Mersey Waterfront Regional Park. The total bid comprises capital of £11,512,438 and revenue of £370,144 in years 0-4. The capital bid comprises the following elements:
Construction 11,159,838 Site Investigation 50,000 Fees 302,600
TOTAL 11,512,438
1.7The development of the project has been phased deliberately to minimise risk and the financial exposure of capital funders as well as the City Council in its role as accountable body for the project.
1.8The approval and expenditure of the stage 1 funding has effectively enabled the planning application and HRO to be submitted as well as the completion of the Environmental Statement - involving intensive consultation with key stakeholders such as English Nature.
1.9The greater certainty about the scheme’s deliverability has also increased the engagement with the cruise and tourism sectors and the interest on the part of a major Cruise operator to name a vessel in Liverpool in April 2005. This would provide a major opportunity not only to glean economic benefit from the project (increased visitors, prestige etc) but also launch the facility into the 2005 cruise season and enable it to ‘hit the ground running.’
Current Position
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.