Resources Select Committee 2005/2006 agreed this item on Wednesday 17 March 2004. Below is the council's own wording, with the papers it was decided on.
Agreed that – The report be noted; and consideration be givenat the next meeting to the powers available to the Council and the steps, which can be taken, to bring back into use vacant properties throughout the city and appropriate officers from the Regeneration Portfolio and the Revenues and Benefits Service be invited to attend the meeting and make a contribution.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Report to Resources Select Committee 2005/2006, 15 pages
Purpose of report
To brief members on the further progress of service developments being implemented within the Revenues, Benefits and Counter Fraud service areas, the current performance of these services and progress towards achieving national standards in the Benefits Service.
Recommendation
That Members note the contents of this report.
Executive summary
Revenues, Benefits and Counter Fraud Services have undertaken a major change programme under the contract agreed between the City Council and Liverpool Direct Limited. The change programme has seen the Service introduce electronic document management and replace its core processing systems.
The service areas have continued to make progress in reducing the work backlogs that resulted from a planned six-week period of downtime during the process of conversion to new ICT systems.
The benefits service has completed a detailed assessment of its standing against DWP National Standards for Housing and Council Tax Benefits. The self- assessment has been presented to the Benefits Fraud Inspectorate, which is currently undertaking an inspection of the service in The City of Liverpool RBS/20/03 accordance with requirement to inspect all local authorities every three years.
The benefits service is currently implementing plans for the replacement of the requirement of customers to periodically complete renewal application forms with a new risk-based review and intervention scheme.
There are a number of remaining activities to develop and enhance the new ICT systems that remain underway and these have been drawn together into a single programme of activity that is being co-ordinated and delivered by Liverpool Direct Limited.
4 Information
4.1Liverpool Direct Limited
The decision making for claim assessment, part of the Benefit Service, will become part of the contractual responsibility of LDL. . This will mean there is a requirement under the Contracting Out (Functions of Local Authorities) Regulations 2002 that 10% of these assessments are checked by the City Council. A new team to undertake these checks is being established and a dedicated database for recording the outcome of the checks has been constructed.
The Service will continue to be monitored through the Service Review meetings chaired by Phil Halsall, Executive Director who is the lead client.
4.2Change Programme Management
The major technology improvement projects of the change programme have now been successfully delivered by LDL. There remain a number of developments and projects which will be completed in the first three quarters of coming financial year including the roll out of document imaging to Education Awards and Business Rates functions and a number of enhancements to the functioning of the new I-World system. These developments are being managed through a dedicated programme board. The City of Liverpool RBS/20/03 4.3 People and Organisational Performance
The service areas continue to embrace “The Liverpool Way” to help ensure that our people are invested in to help drive up the performance of the services. Specific investments in developing improved staff management have been made through a number of initiatives including a programme of training in coaching skills for team leaders and participation in the City’s new Leadership Academy. This activity supports enhanced performance management, better staff communication, and staff involvement in developing and improving the services. Work on improving training and participation has supported LDL and the Council in its achievement of IiP status.
4.4Performance
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.