Human Resource and Payroll Service

Agreed Committee 1 paper

Resources Select Committee 2005/2006 agreed this item on Wednesday 17 March 2004. Below is the council's own wording, with the papers it was decided on.

Item89

Resolved

Agreed that the progress be noted and a further report be submitted to the next meeting.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Resources Select Committee 2005/2006, 4 pages

Purpose of report

1. To report upon the progress in establishing the control arrangements in respect of the replacement HR & Payroll System,

Recommendation

2. That the actions being taken to improve the HR & Payroll System control environment be noted.

INFORMATION:

3. The Committee will recall, at its meeting on the 10th December 2003 it considered a report (FMS/60/03) identifying the actions being taken to improve the HR & Payroll System internal control environment. The following are the key Service Improvement Objectives and associated target dates identified in December 2003.

Service Improvement Objective Target Date

Development and availability of revised payroll January accounting information for Service managers and Head 2004 Teachers. (#)

Completion of Service establishment structures onto March Oracle HR & Payroll database. (*) 2004

Full reconciliation of payroll accounting information to March the General Ledger for 2003/04. (#) 2004

Completion of establishment of key control environment March for HR & Payroll systems. (*) (#) 2004

Verification of personal details by employees. June 2004

Completed roll out of self service HR system for June 2004 managers.

Recovery of overpaid employees pay relating to June 2004 2003/04 or prior. (#)

2 4. Those key improvement objectives marked (*) are to be the subject of further reviews by Internal Audit over the period January to March 2004.

5. Those key improvement objectives marked (#) will be subject to review by the Council’s External Auditors as part of their Audit of the Council’s Accounts and supporting systems and internal control.

PROGRESS REPORT

6. In respect of those objectives with a target date of on or before March 2004, the current position is as follows:

Development and availability of revised payroll accounting information for Service managers and Head Teachers

7. Service managers and Head Teachers have now received financial information relating to payroll data for all months up to and including the end of February 2004.

8. In addition, the additional information that schools requested relating to the provision of a pay code analysis is now provided on a monthly basis – the provision of this information commences with the month of December 2003.

9. Further financial information for schools relating to journalised adjustments carried out during this financial year is now also provided on a monthly basis and in a form agreed with Schools.

Completion of Service establishment structures onto Oracle HR & Payroll database

10. With the exception of Education, Libraries & Sport Portfolio, service establishment structures have now been completed and submitted by Service Portfolios.

11. It is currently anticipated that all data should be collected and entered onto the Oracle HR & Payroll database in time for the April 2004 payroll run.

3 Full reconciliation of payroll accounting information to the General Ledger for 2003/04

12. The payroll accounting information for the months of July 2003 to February 2004 are fully reconciled. However, there are continuing reconciliation issues relating to the payroll accounting information for April to June 2003. Officers are continuing to investigate the inconsistencies.

Completion of establishment of key control environment for HR & Payroll systems

13. A schedule of the required key controls has been drawn up and shared with Auditors. A review is currently being undertaken to ascertain that all the required key controls are in place and, where appropriate, responded to. In addition, a risk assessment is being undertaken to ensure that any high risk weaknesses and controls are addressed as a priority.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Human Resource and Payroll ServiceReport 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Human Resource and Payroll ServiceThis decision
  2. Human Resource and Payroll ServiceAgreed
  3. Human Resource and Payroll Service Development PlanAgreed
  4. Human Resource and Payroll ServiceAgreed
  5. Replacement of Human Resource Payroll SystemAgreed
  6. Replacement of Human Resources Payroll ServicesAgreed

More from Liverpool Resources Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
5 Apr 2006 Minutes of the Last MeetingsAgreed that the minutes be approved. Agreed Open
5 Apr 2006 Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... Agreed Open
5 Apr 2006 Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... Agreed Open
5 Apr 2006 Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. Agreed Open
5 Apr 2006 Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies