Risk Management

Agreed Committee 1 paper

Resources Select Committee 2005/2006 agreed this item on Wednesday 17 March 2004. Below is the council's own wording, with the papers it was decided on.

Item88

Resolved

Agreed that the progress be noted and support be given to the proposal to engage all senior management teams and the Executive Board.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Resources Select Committee 2005/2006, 5 pages

Report to select committees

Liverpool City Council

Report to: Resources Committee

Subject: Risk Management/CPA

Report no:

Date: 17 March 2004 Reporting officer: Eric Wilkinson

Contact officer: Steve Wilkins Ext: 233 4631

Ward: N/A – Corporate Issue 1. Purpose and recommendations This report is to appraise members of the progress made to date and it is recommended that the committee confirm their support for the engagement of all senior management teams with the task of improvement in this key area.

2. Relevant background information The Council as part of developing and moving forward with Risk Management is seeking to improve the CPA rating from level 2 to level 4. In order to achieve this there needs to be in place procedures which are effective in meeting the requirements of both the aims of the organisation and the Audit Commission who have the task of seeking evidence as part of the assessment process.

3. Key issues To embed the risk management process into the workings of senior management teams including the Executive Management Team. To embed the process into service areas. Initially, the focus of these groups is to apply the risk management process to those areas of improvement outlined in the Performance Management database. To embed the process into the workings of the Executive Board.

4. Conclusions That in order to achieve the improvement sought in the next twelve months the active involvement of senior management teams and the Executive Board is needed. A timetable is outlined in the attached report.

5. Key to any abbreviations used None

6. Documents attached Appendix 1 – Progress with Risk Management Appendix 1 Progress with Risk Management

1. Introduction

The priority and the target, is to ensure full and consistent implementation of a risk management culture throughout all levels of the organisation with the aim of achieving the following: • An increase in the awareness of elected members and staff towards business risks. • Development of a risk management culture Council-wide. • To have in place effective processes throughout the Council to identify, quantify, prioritise and manage business risks.

2. Policy and Strategy

The Council has in place a corporate policy and strategy for risk management approved by members. Senior management teams have been made aware of both and it has been added to the intranet via a link from the Performance Management Database. Separate pages for risk management are being added.

3. Training

Training in the understanding of the risk management process has been delivered to the senior management groups with the help of external consultants. An officer has been made responsible for the further provision of training to help senior managers move forward with the process and facilitate the identification, quantification, prioritisation and monitoring of risks by the Executive and Senior Management Teams. This will be extended to include the Executive Board and members through the Executive member for Resources.

4. Risk Registers

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk ManagementReport 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Risk ManagementThis decision
  2. Risk Management UpdateAgreed
  3. Risk Management UpdateAgreed
  4. Risk Management UpdateAgreed
  5. Adoption of Liverpool's Local Flood Risk Management Strategy (HCS/11)Approved
  6. Risk Management StrategyApproved

More from Liverpool Resources Select Committee 2005/2006

All decisions
MeetingDecisionOutcome
5 Apr 2006 Minutes of the Last MeetingsAgreed that the minutes be approved. Agreed Open
5 Apr 2006 Called In Item - Percy Street/Upper Parliament Street/Parliament StreetAgreed that in view of the concerns expressed by members, consideration of this proposal be deferred pending the subm... Agreed Open
5 Apr 2006 Response to Motion - Properties in Newsham ParkAgreed that the Executive Member for Resources be requested to ensure that all long term vacant Council properties in... Agreed Open
5 Apr 2006 Revenues and Benefits Service PerformanceAgreed that the content of the report be noted. Agreed Open
5 Apr 2006 Green Paper - A New Deal For Welfare Empowering People to WorkAgreed that – a) The contents of the report be noted; b) The views of the Committee, particularly in relation to the ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies