Resolved that – (i) the development of the City Council’s Integrated Waste Management Strategy should be finalised by the end of May 2004. (The final timing will be linked to the timing of the receipt of the Merseyside Strategy). The development of the Integrated Waste Management Strategy should be undertaken with wider public consultation; (ii) the existing Regeneration and Environment Select Committee Working Party be retained and given the appropriate authority to scrutinise the development of the City Council’s Integrated Waste Management Strategy; and (iii) Officers be instructed to advise Shanks Waste Services of the Executive Board’s view that the Authority should wait until the development and agreement of the City Council’s Integrated Waste Management Strategy before submitting the City Council’s formal response to the proposal.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Shanks Waste Services (SWS) have prepared a detailed study of the potential development of improved facilities for long term waste management facilities in Liverpool, in partnership with Liverpool City Council. The Regeneration and Environment Select Committee was asked by the Executive Board to adopt a detailed scrutiny brief to oversee the development of the proposals.
On the 16th October 2003 the Regeneration and Environment Select Committee reported back to the Executive Member for the Environment on the outcome of the Committee scrutiny of the Shanks Waste Services feasibility study.
The Executive Member for the Environment supports the Committee findings and recommends the actions set out in this report.
A full report of the Committee findings, report EDR/264 /03 is attached as Appendix A.
Executive Member/Director recommendation: Councillor Richard Oglethorpe / Charlie Parker
(i) The development of the City Council’s Integrated Waste Management Strategy should be finalised by the end of May 2004. (The final timing will be linked to the timing of the receipt of the Merseyside Strategy). The development of the Integrated Waste Management Strategy should be undertaken with wider public consultation;
(ii) The existing Regeneration and Environment Select Committee Working Party should be retained and given the appropriate authority to scrutinise the development of the City Council’s Integrated Waste Management Strategy; and
(iii) Officers be instructed to advise Shanks Waste Services of the Executive Board’s view that the Authority should wait until the development and agreement of the City Council’s Integrated Waste Management Strategy before submitting the City Council’s formal response to the proposal.
Key Decision?
Yes
Forward Plan
Yes
Implementation effective from Immediate
Timescale for action
Liverpool City Council has until March 2005 to work within the terms of the Shanks Waste Services Letter of Intent to develop the project and reach formal agreement with SWS. This date was set from 2 years from the receipt of the report.
The City Council have also undertaken to advise SWS of whether the feasibility study, as presented, satisfactorily covers the requirements of the Letter of Intent. This date was set for 3 months from delivery of the finished report. SWS have verbally agreed to extend this deadline to the end of the development of the IWMS work as recommended in this report.
Reason(s) for Recommendation
To optimise the effectiveness of the City Council’s decision making on the long- term development of Waste Management facilities.
Alternative options considered Alternative Option One : To determine the feasibility, or otherwise, of the SWS proposals immediately.
Two specific outcomes of the Committee scrutiny militate against this action.
First, since work started on the feasibility study, the MWDA have made significant progress in developing an integrated strategy on a sub-regional basis. The final recommendations were presented in December 2003. It is considered reasonable to await the outcome of a full scrutiny of this MWDA work.
Second, the SWS proposals to date have been premised upon a reasonably low rate for the collection of dry recyclables ( circa 20%). Members required further detailed work to be done on the potential for far higher collection rates. Clearly this rate will affect the planning figures for the effectiveness of any proposed treatment plant.
A combination of the above two pieces of work will enable the City Council to develop its own formal Integrated Waste Management Strategy, within which context the SWS feasibility study can be addressed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.