Resolved
Resolved that the individual allocations of the remaining Schools Access Initiative capital funding for 2003/04 as set out in the report submitted, be approved.
Executive Board approved this item on Friday 2 April 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the individual allocations of the remaining Schools Access Initiative capital funding for 2003/04 as set out in the report submitted, be approved.
In 2003/04 the City Council received an allocation of £725,000 capital funding under the Schools Access Initiative (SAI) programme aimed at improving accessibility in schools.
At the outset of the financial year £500,000 of the SAI funding was allocated to finance the second phase of works at Phoenix Primary to provide sufficient inclusive accommodation at the school to incorporate the children from Acorn Nursery School. These works are due to be completed by 8 April.
In addition, £27,000 was allocated to finance additional costs relating to the installation of a lift at Mosspits Infants.
In order to consider the allocation of the remaining £198,000 for 2003/04 and the 2004/05 allocation of £560,000 schools were requested to submit a copy of their access audits together with a copy of their accessibility action plan. To date, 44 audits for the Community sector and 32 for the Voluntary Aided sector have been returned.
The level of funding that is made available from Central Government is such that the SAI can only meet a small part of the cost of the works required to improve the accessibility of the City’s schools. As a consequence the following criteria were used to arrive at the basis of allocation of the remaining 2003/04 funds:
• The school is identified as a priority in terms of its importance to the Inclusion Strategy.
• The school requires physical alterations because the immediate needs of disabled pupils or members of staff are not currently catered for
• The school has significant immediate priority works identified by the audit that can not be reasonably tackled through the use of the school’s Devolved Formula Capital allocation alone because of the level of cost. • The school must have submitted an access audit or plan to be considered for 2003/04 funding.
• Priority initially given to primary schools for the balance of 2003/04 funding.
In respect of this last point, it is recognised that the cost of resolving accessibility issues in some secondary schools is significant particularly if the audit identifies the need for a lift. One or two major items for a secondary school could therefore use up most of the remaining 2003/04 SAI allocation.
The redevelopment of secondary schools under the Building Schools for the Future programme will ultimately ensure that all secondary schools are fully accessible. In addition, the allocation of the funding for 2004/05 and 2005/06 will ensure that the most urgent needs of secondary schools are considered as part of future strategy.
On the basis of the criteria set out above the following allocations are recommended (a summary table is attached as Annex A):
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Schools Access Initiaitve (LL/63)Report | 8 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.