Resolved
Resolved that the bids submitted be approved and if funding from the Department of Constitutional Affairs is secured they will form part of the Approved Capital Programme.
Executive Board approved this item on Friday 20 August 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the bids submitted be approved and if funding from the Department of Constitutional Affairs is secured they will form part of the Approved Capital Programme.
CITY STATUS – PUBLIC RES/8 Portfolio: Resources Executive Member/Director: Councillor Keith Turner/Phil Halsall Date of submission: Subject: Merseyside Magistrate 4th August 2004 Court – Information Technology Equipment – 2004/05
Report No: Contact Officer: FMS/41/04 Debbie Crosthwaite [email protected] Tel: 233 5396
Executive Summary: The Department of Constitutional Affairs (DCA) requires the Merseyside Magistrates Courts Committee (MMCC) in conjunction with all the Merseyside Authorities to submit bids to secure funding for capital expenditure on information technology equipment.
The purpose of this report is to advise members of and to seek support for the bids that the MMCC are to submit for the purchase of IT equipment in 2004/05.
The bids are as follows: £ Anti – Virus Software Licensing 3,600 LCIS User Group Enhancements 10,000 EQUIS User Group Enhancements 20,000 DREHMS User Group Enhancements (DVLA) 6,000 VP/FPO System Enhancements – Fixed Penalty 2,997 Xerox P55 VMFLC Photocopier 4,965 Post Opening Machine 6,000
Total 53,562
Executive Member/Directors' recommendation (Councillor Keith Turner)
That the bids submitted be approved and if funding from the DCA is secured they will form part of the Approved Capital Programme.
Key Decision Yes Forward Plan/5 days notice/special urgency: Not included an appropriate notice will be published
Implementation effective from: 27 August 2004
Timescale for action: The approval for funding is time limited for 2004/05 only therefore, expenditure must be incurred before the end of the financial year.
Reason(s) for Recommendation : To enable the MMCC to ensure the continued efficient provision of the Magistrates Court Service.
Alternative options to be considered: There are no alternative options to be considered. The MMCC carefully prepare the bids and submit those with the highest priority. If Liverpool City Council does not agree to support the bids and the other Merseyside Authorities do then the MMCC can make a determination to still go ahead.
Consultation: Not applicable
Financial Implications: The total value of the bids is £53,562. If approved the funding for the expenditure will be a government grant of 80% (£42,850) and a supported capital expenditure (SCE) borrowing approval of 20% (£10,712).
Sefton Council are the lead authority for Merseyside Magistrates Court and the initial expenditure will be incurred by them. Sefton Council will claim the 80% grant. The remaining 20% is then allocated between the Merseyside Authorities based on the Formula Spending Shares. The amount that would be charged to Liverpool in respect of these bids would be £3,840, funded by the SCE borrowing approval.
As this is an SCE borrowing approval there will be no financial implications for Liverpool. The revenue costs associated with the additional borrowing will be covered by an increase in the Revenue Support Grant via the capital financing element of the grant distribution mechanism.
Best Value: There are no direct best value implications.
Equality Implications: There are no direct equality implications.
Corporate Strategy: Not applicable Budget and Policy Framework: Conforms
Community Safety Implications: There are no direct community safety implications.
Report attached: Not applicable
Background papers: The MMCC have prepared the bid for each scheme. Copies are held in Financial Management Services.
Signature:……………………………. Date:………………………………….
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Merseyside Magistrate Court: Information Technology Equipment: 2004-05 (RES/8)Report | 3 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.