2004/05 Local Safety Schemes Programme and Priority List for Traffic Calming in Liverpool (REG/18)

Approved Executive 1 paper

Executive Board approved this item on Friday 20 August 2004. Below is the council's own wording, with the papers it was decided on.

Item27i

Resolved

Resolved that - (i) The approved local safety schemes, started in 2003/04, requiring completion in 2004/05 with an estimated value of £706K, be funded from the current year’s budget allocation of £1 million for such schemes; (ii) approval be given for the Highways Management Service Manager to commit expenditure on new schemes from the draft programme of local safety schemes detailed in this report, to be started in 2004/05, and funded from the balance (£294K) of the current year’s budget allocation for such schemes; (iii) expenditure of £593K required to complete the schemes started in 2004/05 be regarded as a first call on the 2005/06 allocation of resources to the Transportation Capital Programme; and (iv) approval be given to the new traffic calming priority list detailed in the report submitted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 23 pages

Executive summary

The attached report seeks approval to:

a) Implement the schemes listed in the 2004/05 Local Safety Schemes Programme (LSSP), to be funded from this year’s budget allocation of £1 million for such schemes; and

b) The new traffic calming priority list detailed in the report.

Executive Member/Director recommendation: Councillor Peter Millea/Executive Member for Resources/Charlie Parker

That -

(i) The approved local safety schemes, started in 2003/04, requiring completion in 2004/05 with an estimated value of £706K, be funded from the current year’s budget allocation of £1 million for such schemes;

(ii) approval be given for the Highways Management Service Manager to commit expenditure on new schemes from the draft programme of local safety schemes detailed in this report, to be started in 2004/05, and funded from the balance (£294K) of the current year’s budget allocation for such schemes;

(iii) expenditure of £593K required to complete the schemes started in 2004/05 be regarded as a first call on the 2005/06 allocation of resources to the Transportation Capital Programme; and

(iv) approval be given to the new traffic calming priority list detailed in the report submitted.

Key Decision?

Yes Forward Plan

Yes

Implementation effective from

13 August 2004

Timescale for action

It is anticipated that all of the local safety schemes listed in this report with the exception of the Parkstile Lane Area/Orwell Road Area traffic calming schemes will be started and completed in the current financial year. It should be noted that £25K of design fees will be incurred in 2004/05 on developing a £200K package of schemes for implementation as part of the 2005/06 LSSP.

It is essential that the new traffic calming priority list for 2004/05 is approved so that:

I. Design and consultation can proceed on the new Parkstile Lane Area traffic calming scheme. It is also proposed to undertake design work on the Orwell Road Area traffic calming scheme in the current financial year as this scheme is ranked at position two on the new traffic calming priority list. Public consultation on the Orwell Road Area scheme will only take place in the current financial year if there is slippage in the 2004/05 LSSP and the Housing Market Renewal Initiative proposals for this area are compatible with any proposed traffic calming measures and their implementation timetable. II. The anticipated casualty reduction from the schemes can assist the City Council in meeting both the 2004 Local Public Service Agreement and national 2010 road casualty reduction targets.

Reason(s) for Recommendation

The implementation of the local safety schemes detailed in this report will assist the City Council in meeting both the 2004 Local Public Service Agreement and 2010 national road casualty reduction targets.

Alternative options to be considered

None

Consultation

All local safety schemes including traffic calming schemes are subject to extensive public consultation with Ward Councillors, Area Committees, local residents, emergency services and other approved/affected bodies. Monitoring

Financial – Monitoring of the LSSP will be undertaken on an ongoing basis throughout the year by Officers from both the Highways Management Service and Regeneration Finance. Any changes in the proposed expenditure profile will be submitted to the appropriate Board(s) for approval.

Programme Delivery – Officers from Highways Management will be responsible for the implementation and monitoring of the programme as set out in this report. Any amendments to the approved programme will be submitted to the appropriate Executive Member for approval.

Financial implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2004/05 Local Safety Schemes Programme and Priority List for Traffic Calming in Liverpool (REG/18)Report 23 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
MS
Councillor Mike Storey CBEChair, apologies
WB
Councillor Warren BradleyMember, present
JC
Councillor Jeremy ChowingsMember, apologies
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, apologies
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
RO
Councillor Richard OglethorpeMember, apologies
KT
Councillor Keith TurnerMember, apologies
SD
Sir David HenshawOfficer, present
PH
Phil HalsallOfficer, apologies

All 21 on the meeting page

On this subject at Liverpool

Search all
  1. 2004/05 Local Safety Schemes Programme and Priority List for Traffic Calming in Liverpool (REG/18)This decision
  2. Old Swan Ward - Local Safety Scheme - Binns Road / Pighue Lane AreaApproved
  3. West Derby Ward - Local Safety Scheme - Mill LaneApproved
  4. West Derby Ward - Local Safety Scheme - Mill Lane West DerbyDecided
  5. Church Ward - Calderstones Road - Local Safety SchemeApproved
  6. West Derby Ward - Local Safety Schemes - Mill Lane, West DerbyDeferred

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies