Resolved
Resolved that the City Council accept a free surrender of the existing lease and grants Crystal Clear Limited a new lease for 125 years upon payment of a premium of £129,481 plus surveyor’s fees of £7,094 and legal fees of £5,675.
Executive Board decided this item on Friday 15 October 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the City Council accept a free surrender of the existing lease and grants Crystal Clear Limited a new lease for 125 years upon payment of a premium of £129,481 plus surveyor’s fees of £7,094 and legal fees of £5,675.
This report has been prepared to seek authority for a proposed surrender and renewal of the lease of 34 Rodney Street, Liverpool 1, shown edged black on the attached plan.
34 Rodney Street is held by way of a lease for 99 years from 3 May 1935 at a peppercorn rental. The property is a three storey Victorian mid terrace building of brick and slate construction and is currently used as offices.
The current leaseholder is Crystal Clear Limited. The property requires refurbishment and in order to attract the finance necessary to facilitate such improvements the leaseholder needs to extend the length of his lease. It has been agreed with the tenant that an agreed schedule of refurbishment works will be carried out within the first 6 months of the new lease. The lessee proposes to use the property for offices and residential.
Following negotiations terms have been provisionally agreed to accept a free surrender of the existing lease and grant a new lease for 125 years in consideration of a premium payment of £129,481 at a peppercorn rental thereafter, plus surveyor’s fees of £7,094 and legal fees of £5,675.
The valuation was prepared on 20 August 2004 and is valid for 3 months.
The proposed transaction has been negotiated by 2020 Liverpool Limited, who certify that this proposal represents the best price reasonably obtainable as at 23 August 2004. Executive Director recommendation (Charlie Parker)
That the City Council accept a free surrender of the existing lease and grants Crystal Clear Limited a new lease for 125 years upon payment of a premium of £129,481 plus surveyor’s fees of £7,094 and legal fees of £5,675.
Key Decision?
No
Forward Plan/5 days notice/special urgency
No
Implementation effective from
22 October 2004
Timescale for action
The City Solicitor will be instructed to complete documentation at the earliest opportunity.
Reason(s) for Recommendation
A capital receipt will be generated and the property will be refurbished.
Alternative options to be considered
Refuse to grant a new lease. This would not encourage the proposed improvement of the property.
None
Capital 2004/2005 Premium £129,481 Revenue 2004/2005 Surveyors Fees £7,094 Legal Fees £5,675 The premium will contribute to the City Council’s capital receipts forecast and the surveyor’s fees and legal costs will contribute to existing revenue budget targets.
Best Value:
The Operations Manager Land and Development Services considers Best Value to be demonstrated as the surrender and renewal of this property will secure its refurbishment.
None.
Corporate strategy:
The negotiation of an extended lease will generate a capital receipt and accords with the Corporate Strategy requirement of the efficient use, rationalisation and management of property assets to secure regeneration objectives.
Budget and Policy Framework
Yes
Community safety implications:
None. Report attached
No Background papers
Correspondence between 2020 Liverpool Limited and the agents representing the leaseholder.
Signature: …………………………. Signature: …………………………. (Executive Member) (Executive Director)
Date: ………………………… Date: ………………………….
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
34 Rodney Street (RES/21)Report | 4 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.