Resolved

The Board considered – (i) the following decision of its meeting held on 17 September (Minute No. 45(b)) in relation to Merseytram Line 2 “Resolved that - 1. Be endorsed a tram alignment that supports the regeneration proposals in the Eastern Approaches SIA; 2. Merseytram Line 2 proposals be not endorsed as the next expansion of Merseytram ; 3. Officers undertake a detailed appraisal of a hybrid Line 2/3 option, in partnership with Merseytravel , and report back on the outcome within 3 months; and 4. That the City Council agrees in principle to support the proposed Line 3, subject to the route changes highlighted above, as the next potential expansion of the Merseytram network.”, which had been called in by Councillors Steve Munby , Rose Bailey, Steve Rotheram , Jane Corbett and Joe Hanson for the reason that “To scrutinise the reason for change of Council Policy” and was considered by the Regeneration and Environment Select Committee at its meeting held on 14 October. (ii) A recommendation of the Regeneration and Environment Select Committee that the points raised in relation to Merseytram Line 2 be referred to the meeting of the Executive Board on 15 October. Resolved that – (i) this Executive Board reiterates its commitment to progress Merseytram Line 2; (ii) in order to progress Line 2 alongside Line 1, the Department of Transport be requested to make an immediate announcement on the approval on Line 1; (iii) This Executive Board notes – · that Merseytravel sought views of the City Council and other partners on the proposed Line 2 to which the Council responded; and · the Chief Executive of the City Council contacted the Chief Executive of Merseytravel on 10 September advising him of the Council’s views on Line 2 and notes with disappointment that there was no response received prior to the Executive Board meeting on 17 September; (iv) this Executive Board is further disappointed at the manner in which one of the bidding companies, SERCO, has chosen to blame the City Council’s response to Merseytravel’s consultation exercise, as its reason for withdrawing from the bidding process and in fact it has now emerged, that SERCO’s major financial backer, the MITSUBISHI corporation had withdrawn from the consortium some two months earlier; (v) this Executive Board is surprised that the letter from SERCO withdrawing from the bidding process was not shared with the Chief Executives’ and Leaders’ on Merseyside before it was made public at a press conference; (vi) the decision of the Executive Board of 17 September as set out above be withdrawn; and (vii) the Council looks forward to working with Merseytravel to deliver a world-class tram system as quickly as possible.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 8 pages

CITY STATUS – PUBLIC REG/ 33

Portfolio: Regeneration Executive Director: Charlie Parker

Date of submission: Subject: 17 September 2004 Merseytram Line 2 Response to Consultation

Report No./Background papers Contact officer: EDR/ 191 /04 Tom McCabe Tel: 225 3410

Executive Summary Introduction

1. The first mention of a three line rapid transit network was made in the Provisional Local Transport Plan (LTP) submitted to the Government in July 1999. This recognised that further work was needed to develop proposals for an LRT network.

2. In early 2000, Merseytravel’s consultants Steer Davies Gleave (SDG) undertook a study to identify scheme costs, priorities and programmes for the first Local Transport Plan. The study entitled “Merseyside Local Transport Plan, The Way Forward – Liverpool, South Sefton and Knowsley Study Area” was a two stage process.

3. Stage 1 included a review of technologies, radial and orbital public transport corridors and a first ‘sift’ of potential schemes to be taken forward for further appraisal. The report states that the initial ‘sift’ was based upon an assessment which addressed criteria such as technical feasibility, economic viability or environmental impact.

4. This was followed in mid 2000, by the Stage 2 study which completed the appraisal of the shortlisted corridors and identified potential schemes. This work, entitled Merseyside Light Rapid Transit Annex E Submission, was presented to the Government in July 2000. This included a transport, social, regeneration and an outline cost-benefit assessment of each corridor. The analysis confirmed the preferred choice of light rail (tram) technology and the ranking of the routes was almost identical for each mode with the routes to Kirkby (Line 1) and Prescot (Line 2) producing the best results. It therefore concluded:-

Line 1: the route to Kirkby Line 2: the route to Prescot and

Line 3: the route to Liverpool Airport via Menlove Avenue (alternative Mather Avenue or City Line to Allerton Interchange)

5. In December 2000, the Government awarded conditional approval to Merseytram Line 1, subject to the completion of statutory procedures based upon this Annex E document. A Public Inquiry took place in April/May 2004 and the outcome of the Secretary of States decision is expected in December 2004.

6. However, the Annex E document noted that:-

“Substantial growth is projected for Liverpool Airport, which is currently poorly served by public transport. On balance, therefore it is considered that a better case can be made for the routes to Speke and the Airport… Further analysis is necessary to confirm this conclusion.”

Development Work on Lines 2 and 3

Line 2

7. In terms of development, both Lines 2 and 3 are some way behind Line 1. In July 2003, Merseytravel submitted an Investment Appraisal for Merseytram Line 2 to the Department for Transport in which they outlined the policy background to the scheme, details of the Line 2 corridor and brief financial and appraisal summaries.

8. Public Consultation commenced on 12th July 2004 for a period of 12 weeks. The City Council has not yet responded to this consultation but has prepared a comprehensive Issues Paper incorporating Member, officer and consultant’s views. Merseytravel has advised that a TWA application will follow the consultation and is expected to be submitted late 2004/early 2005. This will seek a Transport and Works Act order granting the powers to implement the Merseytram Line 2. Work is also progressing on the assembly of land for Line 2 and this has raised a potential number of constraints.

Line 3

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Merseytram Line 2 (REG/33)Report 8 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 18 attended
MS
Councillor Mike Storey CBEChair, present
WB
Councillor Warren BradleyMember, present
JC
Councillor Jeremy ChowingsMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
RO
Councillor Richard OglethorpeMember, present
KT
Councillor Keith TurnerMember, apologies
SD
Sir David HenshawOfficer, present
PH
Phil HalsallOfficer, present

All 18 on the meeting page

On this subject at Liverpool

Search all
  1. Merseytram Line 2 (REG/33)This decision
  2. Merseytram Line 1Noted
  3. Merseytram Line 2 (REG/82)Decided
  4. Presentation - Merseytram Line 2.Agreed
  5. Merseytram Line 1 (REG/32)Agreed
  6. Merseytram Line 2 (REG/33)Agreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies