Resolved that – (i) the opportunity to regenerate Otterspool Promenade and to allow the continuing development of investment proposals as described within the reported submitted be noted; (ii) the potential level of funding from Mersey Waterfront and Objective 1 be noted and to support the submission of grant applications by Mersey Basin Campaign to both funding agencies in due course; (iii) the recommendation that the Mersey Basin Campaign act as applicant agency for external grant funding and as such take on the role of Accountable Body on behalf of Liverpool City Council and other partner agencies, be approved; (iv) the Divisional Manager (Regeneration Programmes) be appointed as the nominated officer for progressing recommendations ( i ) – (iii) above; (v) a member group led by Councillor Barbara Mace be set up to oversee the work ; and (vi) further reports to be submitted to Members in due course.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Mersey Waterfront Regional Park is one of two “big ideas” which emerged from the Action Plan for the City Region 2002 – 2005, a sub-regional programme which sets out the priorities for North West Development Agency (NWDA) investment in Merseyside to 2005. The concept, lead by Wirral Metropolitan Borough Council and developed by The Mersey Partnership on behalf of key partners, has received support from the Merseyside Chief Executives.
Re-branded simply Mersey Waterfront (MW), this report seeks permission to progress a Pride in Promenades project with MW partners, identifying and then investing in key promenade locations across the MW area.
Pride in our promenades
As a Key partner in the Mersey Waterfront (MW) initiative Liverpool City Council (LCC) has been engaged in the development of ‘big’ ideas to transform into fundable projects to fit within the remaining MW business planning period up to 31 March 2006 (referred to as the MW Commencement Period).
Given the ‘waterfront’ theme and the desire at a Merseyside level to capture a range of projects relating to Environmental, Tourism, Economic, Sport and other thematic measures the MW Board (which includes Cllr. Barbara Mace as LCC representative) have expressed interest in supporting two additional projects during the remaining 2 year (commencement) programme period;
• Pride in Promenades • Liverpool Riverlands
The ‘Liverpool Riverlands’ project is a proposed feasibility study requesting funding to support a piece of work that will recommend how best the land-use and mix could be maximised and, how open space could complement development activity (by for example complementing but not including the former Garden Festival site). The area in question stretches from St Michael’s to Cressington Park, and includes the Otterspool area. The project would look into how Riverlands could contribute to the wider visitor destination experience at a sub-regional level.
The vision of the Mersey Waterfront is to transform, energise and connect the Mersey Waterfront and all its assets to create a unique sense of place that attracts people to live, work and invest in Merseyside. The Liverpool Riverlands study will, subject to funding approval, complement the vision for MW. The outcome of this study could lead to future funding from MW, post 2005/6, supporting the transition from the Commencement Business Plan into what could be a longer-term MW initiative. This would depend on the availability of funding from key agencies such as NWDA, Europe and others.
The ‘Pride in Promenades’ project on the other hand is an implementation scheme, developing a range of early actions to improve the appearance and pleasability of the promenade area in S. Liverpool (Otterspool) and a similar area on the Wirral. The Pride in our Promenades project will play a key and highly visible part in achieving the MW ambition.
MW have agreed to act as Sponsor agency on this project, working closely with the Mersey Basin Campaign (who have agreed to act as applicant organisation and accountable body on behalf of the Local Authorities) to develop the project and the partnership necessary to ensure effective delivery and long-term sustainability. The local authorities of Liverpool City Council and Wirral Borough Council are the key delivery bodies and will manage the works, while the MW team will manage internal and external communications – including site branding in collaboration with the applicant organisation and the host Districts.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.