Resolved
Resolved that that the revised risk management policy and strategy be approved be issued to all Members of the Council, Executive Directors, Assistant executive Director’s, Heads of Service and Group Managers.
Executive Board approved this item on Friday 12 November 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that that the revised risk management policy and strategy be approved be issued to all Members of the Council, Executive Directors, Assistant executive Director’s, Heads of Service and Group Managers.
CITY STATUS – PUBLIC RES/28
Portfolio: RESOURCES Executive Member/Director: COUNCILLOR KEITH TURNER/PHIL HALSALL
Date of submission: 27 October Subject: RISK MANAGEMENT 2004 POLICY AND STRATEGY
Report No./Background papers: Contact Officer: STEVE WILKINS Report number TRM/SHW/2/2004 and attachments endorsed by Resources Select Committee are attached
Executive Summary: The Risk Management Policy Statement and Risk Management Strategy of the City Council is periodically reviewed as provided for within it. As a result of the last review changes have been recommended to bring it up to date and these have been endorsed by the Resources Select Committee. In order to give effect to the revisions as Policy of the Council, Executive Board Approval of the revised policy and strategy is required.
Executive Member/Director recommendation (Cllr Keith Turner/Phil Halsall): Keith Turner, Executive Member for the Resources Portfolio and Phil Halsall Executive Director, Resources Portfolio recommend that the revised policy and strategy be approved by the Executive Board and that it be issued to all members, Executive Directors, AED’s, Heads of Service and Group Managers.
Key Decision: No
Forward Plan/5 days notice/special urgency:
5 days notice
Implementation effective from:
19 November 2004
Timescale for action: Immediate Reason(s) for Recommendation: To update a Council Policy
Alternative options considered: Non viable
Consultation: None required but endorsed by Resources Select Committee
Financial implications: None
Best Value: Consistent with best value principles
Equality implications: None
Corporate strategy: Consistent with plans for improving the CPA
Budget and Policy Framework: None
Community safety implications: None
Report attached: TRM/SHW/2/2004 and “A policy and strategy to improve the management of business risks” dated July 2004 Liverpool City Council
Performance management framework:
A policy and strategy to improve the
management of business risks – as
an integral element of corporate,
financial and service planning within
the authority
Date: 28th July 2004 Version 2 Contents Risk Management Policy ................................................................................. 5 Risk Management Strategy ........................................................................... 7 Risk Management Policy
Liverpool City Council is committed to providing services to the Liverpool community, which are of a high quality in the most efficient and cost effective way.
In so doing, the council recognises that it has a duty of care to its stakeholders – its citizens, its customers, its employees and its partners. It has a duty to be efficient, transparent and accountable to local people, and it needs to observe high standards of corporate governance and management.
An essential part of this corporate governance is the way that the council manages the business risks it takes and faces on the community’s behalf. By business risk, the council means anything that can contribute to or adversely affect the achievement of its key objectives and service delivery.
To this end, the council is committed to best practice business risk management to help improve its decision making and its achievement of key objectives. The council’s policy for better business risk management is to:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Policy and Strategy (RES/28)Report | 17 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.