Resolved that – (i) the overall deterioration in the financial position for the City Council and the level of "areas of concern" be noted; and (ii) the additional use of Reserves of £0.824 million, as identified in Annexe F submitted in respect of the General Fund, be approved.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
CITY STATUS - PUBLIC RES/30 Portfolio: Resources Executive Member / Director: Cllr Keith Turner / Phil Halsall
Date of submission: Subject: Financial Review Report 27 October 2004 2004/05 Half Year Contact Officer: Robert Corbett Report No./Background papers AED Financial Management FMS/44/04 TEL: 0151 225 2200 [email protected] Executive summary
This report is intended to advise of the current forecast for the financial position of the current financial year 2004/05 based on information as at September 2004.
General Fund - Revenue Position
This report advises that overall anticipated spending can still be forecast to be within available resources (see General Fund Budget Statement Annexe A).
This forecast is based upon in part the service Portfolio Financial Monitoring Reports, which are to be considered by the appropriate services Select Committees. Those reports identify a range of "areas of concerns" the most significant of which are summarised in Annexe B to this report. These issues are the continuing subject of specific management attention with a view to either avoiding the issue becoming an overspend, or minimising the overspend potential and identifying offsetting or compensatory savings from elsewhere within the overall portfolio budget allocation.
However, after allowing for the use of reserves, the following two areas are of particular concern as it is considered unlikely that all of the potential forecast deficits will be able to be offset or avoided.
Supported Living & Supported Housing
There are a range of significant budgetary pressures, as set out in Annexe B, which are currently forecast to result in the spending on Supported Living and Supported Housing being £3 million greater than allocated resources.
Similar spending pressures are being experienced by all the Core Cities and therefore the majority of the other Authorities are also experiencing forecast deficits in respect of these service activities.
A range of management actions have been identified to mitigate the forecast additional spending. The actions planned will be identified and reported to future meetings of the Social Care & Health Select Committee and the Housing & Community Safety Select Committee. It is expected that the actions taken will have some effect in controlling expenditure but it is unlikely that all of the current forecast additional spending can be avoided and therefore will reduce the Working Balances available at the end of the financial year.
Leisure Services
Annexe B identifies a number of areas where the revenue budget is currently forecast to be overspent. The total revenue overspending is forecast at £0.5 million.
A further concern relates to the ERDF grant anticipated in respect of the refurbishment of St Georges Hall. At the time of preparing this report the External Auditors were not satisfied with the Council’s grant claim and, as such, upto £0.584 million of anticipated grant funding could be at risk.
A range of management actions must be identified to mitigate the forecast additional spending. The actions planned will be identified and reported to future meetings of the Culture & Tourism Select Committee. It is expected that the actions taken will have an effect in controlling expenditure but it is unlikely that all of the current forecast additional spending can be avoided and therefore will reduce the Working Balances available at the end of the financial year.
In addition, expenditure towards the Leisure Services capital programme exceeds the allocated capital resources. The additional expenditure is primarily in respect of the evaluations for a 50 metre pool and the World Discovery Centre at the Central Library for which Council decisions to commit to these projects have yet to be made. Therefore, at present, there is a requirement for the Portfolio to ensure that there are offsetting cost reductions in revenue of £0.3 million to provide the resource necessary to fund the capital expenditure incurred.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.