Resolved that – (i) the final proposal of the Hope Street Public Realm Improvement scheme be approved; and (ii) authority be granted for the Executive Director (Regeneration) to accept a capital grant from North West Development Agency of up to £2,100,000 and from the Environmental Improvement Programme of up to £320,000 for capital funding for the scheme subject to the receipt of offer letters. The City Council will thereby accept the role of accountable body and ensure that each grant is administered appropriately. On receipt of offer letters for capital funding - (i) the City Council’s capital programme be adjusted to reflect expenditure of £450,000 in the financial year 2004/05 and £2,038,000 in 2005/06, with a retention of £62,000 included in 2006/07; (ii) expenditure of up to £2,550,000 be committed; (iii) the City Centre Projects Team Manager be appointed as the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and (iv) expenditure on the contract works stages of the project is only incurred after the receipt of confirmation of funding from the relevant bodies upon which this project relies for income and the finalisation of all other relevant documents.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. The purpose of this report is to provide an update on the Hope Street Public Realm Improvement scheme, including the scope, scale and remit of the proposals and final cost estimates.
2. Liverpool City Council together with Liverpool Vision has been working with retained consultants to finalise the detailed design for the public realm improvement project on Hope Street. This Scheme responded to a Key Priority Action identified in Liverpool Vision’s Strategic Regeneration Framework (SRF) in 2000, and was closely guided by a steering group formed for this project.
3. The objective of the scheme is to maximise the quality of the pedestrian environment whilst maintaining vehicular capacity and access. This objective is complementary to actions proposed under the adjacent Canning Street Controlled Parking Zone. Executive Board Report No. EDR/260/03 outlined key features of the scheme.
4. Sketch proposal for the scheme received approval from the Environment Working Group (EWG) and funding has been secured from NWDA to enable detailed design of the scheme to take place. The detailed design has allowed preparation of an accurate cost estimate for the scheme and enabled an application to be submitted to NWDA for the implementation of the scheme.
5. Detailed design for the scheme was completed in January 2004 following extensive value management and option testing. The estimated cost for the implementation of the project is £2,550,000. The works will be delivered under the City Centre Movement Strategy (CCMS) Framework Contract, which incorporates a ‘Contract Negotiation Stage’ the result of which is an agreed target price for the scheme. The Framework Board has allocated a contractor to the project, and the contract negotiation stage is underway. Although the final Target Cost may vary from the estimated cost currently available, there is not anticipated to be significant variation as the framework rates were used wherever possible during the production of the estimated cost.
6. An application to NWDA for the capital cost of implementing the scheme was submitted for appraisal in January 2004, with the intention of commencing work on site in April 2004. However, the application was not progressed due to the major review of financial commitments that NWDA was undertaking at the time. Appraisal of the application is now in progress, and a decision is expected in early January 2005.
7. A complementary application has been submitted for funding of £320,000 from the Environmental Improvement Programme (EIP) for the enhanced design of the new area of public realm at the junction of Hope Street and Mount Street.
8. The final element of funding for the scheme (£130,000) is specifically for traffic signal improvements and will now be included in the Highways Capital Programme in the 2005/06 financial year. The Highways Manager will ensure that this scheme is first call on the available LCC resources for 2005/06
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.