Resolved that the following amendments to the Stonebridge Business Park Infrastructure project be noted and approved - (i) Liverpool City Council acts as applicant and Accountable Body for £1,268,798 Objective1 funding in respect of Stonebridge Business Park infrastructure phase 1(a) and £4,039,749 in respect of phase1(b); (ii) authority be given to the Executive Directors (Regeneration) and (Resources) to accept the higher ERDF capital grant of £5,308, 547 phased over the financial years 2004/5 to 2007/8 to contribute towards the cost of delivering the scheme; (iii) the £1,268,798 ERDF drawn down through phase 1(a) of the project be re-cycled back into the development as a City Council contribution to the phase 1(b) project; (iv) the City Council’s capital programme be adjusted, to reflect expenditure on this project for a sum up to £5,308,547 phased over the financial years 2004/5 (£1,625,480), 2005/6 (£2,748,190), 2006/07 (£834,977) and 2007/08 (£99,900); on the receipt of the ERDF offer letter from the Government Office North West; and (v) further reports be submitted to Members as and when appropriate to update on progress.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. The purpose of this report is to provide an update on the Stonebridge Business Park infrastructure project for which the city has agreed (EDR 126/04) to act as accountable body for ERDF purposes , and to advise on an amended claim procedure that has been discussed with Govt Office North West. (GONW)
2. The project will enable Liverpool Land Development Company (LLDC) to provide site access, services and infrastructure into Stonebridge Business Park with match funding provided by the North West Development Agency (NWDA). The works are to take place on the former GEC and Sugarbrook sites and NWDA has already incurred £4,975,569 costs to assemble the site and demolish redundant structures - these costs pre-date the ERDF application and were not therefore included as an eligible cost.
3. Since the application was submitted GONW has reviewed the likely level of ERDF spend in 2004 and concluded that there is strong risk of de- commitment from the Objective One programme. To combat this GONW are looking at options to increase ERDF draw down, including retrospection and front loading of ERDF payments. Stonebridge has been identified as one of the projects that could contribute to this.
4. GONW has now requested that the Stonebridge project be undertaken as a two phase project – phase 1(a) being site assembly / demolition and phase 1(b) being the infrastructure development project. The total amount of ERDF across the two phase 1(a) and 1(b) elements has increased by £300,000 and the two phase process will allow £1,268,798 ERDF to be paid out in 2004 against site assembly costs already incurred, rather than waiting for development costs to be incurred in 2005.
5. To achieve this £1,268,798 ERDF will be paid to the City Council under phase 1(a) against expenditure already defrayed by NWDA, and this amount will be re-cycled into the infrastructure element as a City Council contribution to the phase 1(b) project. The City Council will then act as accountable body for £4,039,749 ERDF under the phase 1(b) application
6. The outputs and timescale for development remain unchanged. 7. Delivering the project in the way outlined above will have a neutral effect on the City Council budget but will help the Objective One programme to avoid the threat of decommitment and loss of funds back to Brussels.
Executive Member/Director recommendation. (Executive Members Councillors Peter Millea and Keith Turner /Charlie Parker –
That Members note and approve the following amendments to the project :
(i) Liverpool City Council acts as applicant and Accountable Body for £1,268,798 Objective 1 funding in respect of Stonebridge Business Park infrastructure phase 1(a) and £4,039,749 in respect of phase 1(b)
(ii) authority is given to the Executive Directors of Regeneration and Resources to accept the higher ERDF capital grant of £5,308, 547 phased over the financial years 2004/5 to 2007/8 to contribute towards the cost of delivering the scheme
(iii) the £1,268,798 ERDF drawn down through phase 1(a) of the project be re-cycled back into the development as a City Council contribution to the phase 1(b) project
(iv) the City Council’s capital programme be adjusted, to reflect expenditure on this project for a sum up to £5,308,547 phased over the financial years 2004/5 (£1,625,480), 2005/6 (£2,748,190), 2006/07 (£834,977) and 2007/08 (£99,900); on the receipt of the ERDF offer letter from the Government Office North West that:
(v) further reports are submitted to Members as and when appropriate to update on progress.
Key Decision:
Yes
Forward Plan
No – appropriate notices will be published in accordance with the constitution
Implementation effective from:
Timescale for action:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.