Liverpool City Council
Executive Board, Friday 7 January 2005

Church Street - Phase 1 (REG/56)

Decided Executive 1 paper

Executive Board decided this item on Friday 7 January 2005. Below is the council's own wording, with the papers it was decided on.

Item106k

Resolved

Resolved that That the Executive Director (Regeneration) be authorised to – (i) adjust the City Council’s transportation capital programme to reflect expenditure and grant income against Church Street Phase 1 to a maximum of £95,000 phased over the financial years 2004/5 and 2005/6; (ii) accept a grant from the Single Regeneration Budget Round 6 (SRB6) up to a maximum of £95,000 for the Church Street Phase 1 project over the financial years 2004/5 and 2005/6; (iii) appoint the Highways Manager as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and (iv) incur expenditure up to a maximum of £95,000 on the Church Street Phase 1.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

Church Street will form one of the final City Centre Movement Strategy (CCMS) projects to be delivered before 2008. The project is vital to create a high quality public realm in the heart of the city centre retail area.

The scheme will link together the Church Street corridor with the Package X public realm project (in Greater Williamson Square and the Cavern Quarter) and the proposed public realm to be delivered through the PSDA project to create a world class retail environment.

The project area can be defined as Lord Street (south), Church Street, Church Alley, Parker Street, Elliot Street, and Houghton Street. See Figure 1.

The project will be delivered in three principal phases: Phase 1: Concept Design Phase 2: Detailed Design and Contract Preparation Phase 3: Construction

This report seeks Members approval to accept an SRB6 grant and commit expenditure to deliver Phase 1 of the project.

It is proposed that a detailed brief is issued to 2o2o Liverpool to undertake this commission. An urban design consultant will also be procured to lead on the design aspects within Phase 1.

The Phase 1 project itself will involve: ƒ preliminary consultation with all stakeholders ƒ the preparation of concept designs and ideas with cost estimates ƒ the approval of concept designs by the Public Realm and Movement Management Team (MMT) and Members ƒ further consultation including public exhibitions ƒ finalisation of concept design and budget Once this concept stage is complete the project will move forward to Phase 2 (Detailed design)

Executive Member/Director recommendation: (Councillors Peter Millea and Keith Turner/Charlie Parker)

That the Executive Director of Regeneration (Charlie Parker) be authorised

to:

(i) Adjust the City Council’s transportation capital programme to reflect expenditure and grant income against Church Street Phase 1 to a maximum of £95,000 phased over the financial years 2004/5 and 2005/6;

(ii) Accept a grant from the Single Regeneration Budget Round 6 (SRB6) up to a maximum of £95,000 for the Church Street Phase 1 project over the financial years 2004/5 and 2005/6;

(iii) Appoint the Highways Manager as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises;

(iv) Incur expenditure up to a maximum of £95,000 on the Church Street Phase 1.

Key Decision?

No

Forward Plan?

N/A

Implementation effective from:

On the receipt of an offer letter from the Cityfocus Board.

Timescale for action:

A funding application for Church Street Phase 1 was approved by the Cityfocus Board on the 25 November 2004.

A brief has been submitted to 2o2o Liverpool and it is anticipated a Target Cost will be agreed before Christmas 2004.

On receipt of the offer letter from Cityfocus and approval from the Executive Board, LCC will award the commission to 2o2o Liverpool in early January 2005.

Church Street Phase 1 (January to May 2005):

Preliminary Consultation January 2005 Initial Concept Design and Cost Estimate February 2005 MMT and Members Approval March 2005 Secondary Consultation April 2005 Public Exhibition April 2005 Final Concept Design and Cost Estimate May 2005

The preliminary consultation will include a design workshop with Members.

It is anticipated Detailed Design (Phase 2) will immediately follow from May to September 2005 with funding bids submitted for the works in Autumn 2005 once a Task Order has been agreed with one of the CCMS Framework Contractors.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Church Street: Phase 1 (REG/56)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Church Street - Phase 1 (REG/56)This decision
  2. St James Methodist Church, High Street, Woolton Village, Liverpool L25 7TE (Woolton Ward)Approved
  3. Former George Henry Lee Building, 51-57 Church Street, Liverpool L1 3AY (Central Ward)Approved
  4. 1-5 Church Street, Liverpool, L1 1DA (Central Ward)Approved
  5. Tree Preservation Order 384 (2009) - Land at St. James Methodist Church, High Street, Liverpool 25 (Woolton Ward)Decided
  6. Central Ward - TRO for Church Street / Lord St areaApproved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open