Item127e

Resolved

Resolved that approval be granted to spend £400,000 on Brougham Terrace Phase 2 from existing agreed NRF to support the installation of a lift, and a range of supporting Disability Discrimination Act works, and interior décoration, £250K of this figure to be spent by 31 March 2005.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Background

Complimenting the improvements to customer access through the development of the City's network of One Stop Shops, Customer Focus Centres have been developed to improve communication between service areas, and to provide a platform for joined up working to assist customers. Cost savings are achieved by reducing accommodation overheads, reducing sub standard buildings and supporting the DDA obligations for the authority.

A report was agreed 23 March 2004 by the Executive Board to redevelop Brougham Terrace (Phase 1) into a Customer Focus Centre refurbishing the building fully with a new voice and data infrastructure, and improved furniture layout to maximise occupancy levels.

To comply with the Disability Discrimination Act No 3 (October 2004), it has been established that this building requires further work to the value of £400,000 (Phase 2) in order to comply and continue internal refurbishment effectively. This will include installation of a lift, review of current access ramp, a review of toilet facilities, décor to aid navigation and viewing panels on main routes etc.

In addition, due to the re-phasing of the Capital of Culture Shop and in order to achieve the required spend deadlines £250K will need to be spent against Brougham Terrace project this year i.e. by 31 March 2005.

A tendering process via Premises Management Unit has been undertaken and detailed costings received to support achieving the recommendations of an access report carried out in August 2004 in line with the authorities DDA commitments. £400K NRF funding has been approved via the UK Programmes team for this phase of the works.

2. Proposal Brougham Terrace Customer Focus Centre – Phase 2

Due to the authorities need to comply with the Disabilities Act of October 2004, it has been identified that this building requires further work valued at £400,000 in order to comply. This will include installation of a lift, review of current access ramp, a review of toilet facilities, décor to aid navigation and viewing panels on main routes etc. With £250K of this figure to be committed to works undertaken by 31 March 2005.

3. Executive Member / Executive Director (Councillor Chris Curry / Phil Halsall / David McElhinney)

That approval be granted to spend £400,000 on Brougham Terrace Phase 2 from existing agreed NRF to support the installation of a lift, and a range of supporting DDA works, and interior décoration. £250K of this figure to be spent by 31 March 2005.

Key Decision?

Yes

Forward Plan/5 days notice/special urgency

No, an appropriate notice will be published.

Implementation effective from

11 February 2005

Timescale for action

Officers to immediately procure the necessary conversion and associated works in a manner which meets the requirements of Contract Standing Orders and Financial Regulations.

Reason(s) for Recommendation

The development of Brougham Terrace into a Customer Focus Centre will further the continued development of the Customer Focus Centre network servicing the whole of the city. This will enhance the opportunity to develop a joined up approach to service delivery to the citizen citywide.

This development contributes to the accommodation strategy allowing us to rationalise the buildings leased and owned by the Council.

Alternative options considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Brougham Terrace Customer Focus Centre (RES/55)Report 4 pages DownloadRead as text

At this meeting

Whole meeting
125Minutes of the Last MeetingsApproved 126Annual Audit and Inspection LetterNoted 127aCounter Fraud (RES/51)Approved 127bPrompt Payment Discount (RES/52)Approved 127cAppropriation of Earmarked Reserve (RES/53)Decided 127dPicton Road Customer Contact Centre (RES/54)Agreed
127eBrougham Terrace Customer Focus Centre (RES/55)This decision
127fWavertree Customer Focus Centre (RES/56)Agreed 127gMagistrates Courts - Building Bids (RES/57)Approved 127hMagistrates Courts - IT Bids (RES/58)Approved 127iMerseyside Public Libraries Purchasing Consortium (LS&C/18)Decided 127jAuthorisation of Anti Social Behaviour Act 2003 Section 30 Powers (CS/4)Decided 127kSustrans Grant for Surface and Access Improvements to the Liverpool Loop Line (REG/61)On the agenda 127lLiverpool JET Review and ERDF bid (REG/62)Approved 127mThe Cityfocus SRB Programme 2004/5, Mid Year Report and Programme Amendments (REG/63)Noted 127nKuumba Imani Centre - additional project costs (REG/64)Decided 127oFormulation and Consultation Process for Proposed Co-ordinated Admission Arrangements for September 2006 (LL/34)Approved 127pConsultation about the Community and Controlled Primary School Admission Policy and the Community Secondary School Admission Policy for September 2006 (LL/35)Approved 127qConsultation on Community and Controlled Primary and Community Secondary School Admission Numbers for September 2006 (LL/36)Approved 127rLand at Woodlee Road/ Lee Hall Road (RES/60)Deferred 127sReorganisation of Primary Provision for Pupils with Complex Learning Difficulties - Phase 2 (LL/38)Agreed 127tCapital of Culture Experience '08 Place' (L/10)Decided 128Education and Lifelong Learning Select Committee - 19 January - Thingwall HouseDecided 130Exclusion of Press and PublicDecided 131aMerseytram Project Update (REG/65)Private

On this subject at Liverpool

Search all
  1. Brougham Terrace Customer Focus Centre (RES/55)This decision
  2. Brougham Terrace Customer Focus Centre (CFC) (M/49)Decided
  3. 8-10 Brougham Terrace (RES/21)Approved
  4. Called in Item - Brougham Terrace Customer Focus CentreAgreed
  5. Brougham Terrace Customer Focus Centre (RES/117)Decided

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies