Resolved that – (i) the progress at mid-year point of the SRB 2004/5 programme be noted; (ii) the capital programme of the City Council be amended to reflect the increased expenditure of £107,624 of SRB projects bringing the total capital expenditure to £2,141,658 which will be financed by SRB grant; and (iii) the revenue budget of the City Council is amended to reflect reduced SRB expenditure of £185,126 and corresponding reduced revenue grant income as outlined in Annex 1 submitted.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to inform Executive Members of changes to the cityfocus, City Centre SRB capital and revenue programmes since approval of the Delivery Plan in July 2004, to report on progress at the mid-year point and to amend the City Council’s Capital Programme in line with financial regulations.
Background
The Executive Board approved the combined SRB and SIA Delivery Plan for 2004/5 in July 2004. The Delivery Plan detailed projects which we anticipated to support and the expected levels of investment. The financial breakdown included £2,307,034 capital and £2,012,189 revenue in 2004/5 to reflect the proposed allocation and spend of SRB resources.
In the Plan, the cityfocus Board stated its intention to retain its flexibility to amend the programme as necessary to achieve overall targets. As a result this report details the amendments required to the City Council’s capital and revenue programmes to reflect the necessary changes to the SRB programme.
Financial Progress
Progress of projects supported by the SRB programme so far this year has been good. The first phase of key public realm works in the city centre is complete and was celebrated with the launch of the Williamson Square fountain. Connecting Liverpool is well underway and the City Centre Inward Investment Programme has brought 400 new jobs to the city. The JET service has assisted over 600 residents from our most deprived areas into jobs. Annex 1 provides details of the revised forecasts for existing projects and additional projects which have been approved since the Delivery Plan by the cityfocus Board and now form part of the programme for the current financial year.
Executive Members Peter Millea and Keith Turner / Director Charlie Parker recommendation
That:- (i) the progress at mid-year point of the SRB 2004/5 programme be noted; (ii) the capital programme of the City Council be amended to reflect the increased expenditure of £107,624 of SRB projects bringing the total capital expenditure to £2,141,658 which will be financed by SRB grant; (iii) the revenue budget of the City Council is amended to reflect reduced SRB expenditure of £185,126 and corresponding reduced revenue grant income as outlined in Annex 1.
Key Decision: Yes
Forward Plan: No appropriate notices will be published in accordance with the Constitution
Implementation effective from: 11 February 2005
Timescale for action: It is important that approval is given to enable smooth delivery of the SIA and SRB programmes for the remainder of this financial year.
Reason(s) for Recommendation: To agree the City Centre SRB programme 2004/5 amendments to the capital and revenue programmes.
Alternative options considered: There are no alternative options for consideration.
Consultation
Consultation has been undertaken with, cityfocus Board and Working Groups, NWDA and Regeneration Finance who have agreed to the proposed amendments to the 2004/5 SRB programme. Financial implications:
The City Council’s budgets will be adjusted as per Annex 1 to reflect changes to the SRB programme. There are no additional requirements for City Council resources.
The City Council’s capital programme will be adjusted to reflect re-profiled expenditure on existing projects and the new approvals in order to ensure that Delivery Plan targets are met. The total cityfocus capital programme will be increased from £2,012,189 to £2,414,658 and the additional £107,624 capital is to be met from a saving in the cityfocus SRB revenue budget. No additional resources are required from the City Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.