Resolved that - (i) the Council’s Capital Programme be amended to include a project provision of £ 2.2 million; (ii) the funding for the Capital Programme to be amended to reflect that the funding is through a combination of £1.4 million NRF, £245K SRB and £555k capital resource; (iii) the Executive Director be authorised to accept the offer of grants from NRF and SRB; and (iv) the Executive Director be authorised to commence spend of project costs totalling £2.2m which includes the fit out of the 08 Place at the cost of £1,422,400.43.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The Executive Board at its meeting of the 28th November 2003 agreed to enter into a lease agreement to develop a Capital of Culture ‘front office’, (‘the 08 Place’). The report also considered the opportunity of integrating the Mersey Partnerships ‘Tourist Information Centre’s’ (TIC’s) into the development. Estimated fit out costs of £900k were included within this report.
A further detailed report outlining the development of the project, integration of TIC’s, operational implications and funding streams totalling £2.2m was submitted to by the Executive Board on 15th October 2004.
Subsequently, contractor sums have been agreed and permission is now sought to commence spend of the £2.2m costs which are made up of £1.4m Neighbourhood Renewal Fund (NRF), £245k SRB and £555k capital resource. The fit out cost being £1,422,400.23.
Leader/Chief Executive recommendation (Councillor Mike Storey, CBE/Sir David Henshaw)
1. The Council’s Capital Programme to be amended to include a project provision of £ 2.2 million;
2. The funding for the Capital Programme to be amended to reflect that the funding is through a combination of £1.4 million NRF, £ 245K SRB and £555k capital resource;
3. The Executive Director be authorised to accept the offer of grants from NRF and SRB; and
4. The Executive Director be authorised to commence spend of project costs totalling £2.2m which includes the fit out of the 08 Place at the cost of £1,422,400.43.
Key Decision?
Yes
Forward Plan No – Appropriate Notices will be served under the Constitution
Implementation effective from 11 February 2005
Timescale for action
As NRF and SRB funding streams are time limited to this financial year, it is vital that work commence immediately. Yes, SRB and NRF funding need to be spent in financial year 2004/2005
Reason(s) for Recommendation
As Above
Alternative options to be considered
N/A
Consultation
N/A
Financial implications
Funding will be lost if not spent in this financial year jeopardising the project.
Best Value:
N/A for this report
Equality implications
N/A for this report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.