Resolved that – (i) the progress regarding the establishment of the Kings Waterfront operating company, be noted; (ii) it be recommended to the City Council that the proposed initial membership of the main Board and the Operational Board as outlined above in section 5 of the report submitted, beapproved ; (iii) the Executive Directors (Regeneration) and (Resources) be authorised to negotiate and accept an ERDF grant offer letter for a maximum of £45,962,000 towards the capital costs of constructing the facility and the City Council’s capital budget be adjusted to reflect the ERDF funding; (iv) the Assistant Executive Director (Regeneration Policy and Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the ERDF grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations; (v) the Chief Executive of the City Council and the Executive Director (Resources), in conjunction with the scheme’s Chief Executive, provide a detailed business plan for the operation of the facility, including any subvention, highlighting revenue implications for the City Council and how risks will be managed on an on-going basis. The Executive Director (Resources) will also make budgetary provision to cover any requirement to repay grant as a result of revenue shortfall in the financial year in which the liability arises; and (vi) the Chief Executive of the City Council and the Executive Director (Resources) should prepare a report on the creation and operation of a Subvention Fund.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of this report is to bring Members up to date with progress on the operational arrangements necessary to support the scheme and to make a number of recommendations which will help secure the construction of the facility before the end of 2007.
2. Introduction
Members have previously considered a number of progress reports regarding the civic facilities at Kings Dock. In particular, previous reports have outlined the key principles regarding the development of the Kings Waterfront and the construction arrangements and financing arrangements have also been determined previously.
Since the last report to the Executive Board, considerable progress has been made regarding the scheme.
3. Key Progress Areas
There are a number of key areas where real progress has been made, all of which will help ensure completion of the project. In particular:
Planning approval was granted by the Council’s planning committee in December 2004 and the Deputy Prime Minister has recently accepted this recommendation without the need for a separate Public Inquiry. The planning permission is in detail for the Civic Facilities element and Car Park with the remainder being in outline.
Substantial progress has been made with our partners, the North West Development Agency (NWDA) and English Partnerships (EP), to finalise the legal documentation in relation to their provision of funding and it is anticipated that this will be in place by the end of March 2005. Negotiations are currently well advanced to secure the necessary ERDF support to construct the facility.
The Council has been utilising the services of the current Chief Executive of the NEC Group to act as an Interim Chief Executive to the proposed scheme. This has enabled the existing documentation and scheme design to be reviewed and appraised from an operator’s perspective.
The Council have recently completed a recruitment process to appoint a Chief Executive to the scheme.
The Authority has been working with Arlingclose Ltd to create a financing arrangement which will enable the Council to take full advantage of any tax breaks available under the Capital Tax Allowances scheme.
The Council has been working with The Mersey Partnership (TMP) to commence promotion of the facilities. The scheme is now featured in all of TMP’s marketing literature and was the centre piece of TMP’s stand at the Confex exhibition at Earls Court. This is a major exhibition which hosts all major conference and exhibition venues across the UK.
4. Next Steps
Whilst excellent progress has been made, it is vital that this is continued in order to ensure opening of the new facilities in December 2007. Key areas which need to be further developed in detail over the coming months include:
Governance Arrangements; Completion of the legal documentation; Formal commitment of the Council to the draft Business Plan; Completion of the ERDF requirements; Finalisation of the funding agreement and Capital allowances scheme; and Creation of a Subvention Fund
5. Governance Arrangements
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.