Resolved that – (i) Members reaffirm their in principle support for a three line tram network servicing Liverpool and the surrounding areas; (ii) Members note receipt of the notification of intention to apply for the Line 2 TWAO under Section 1 of the Transport and Works Act 1992 in order to obtain the necessary powers to construct and operate Merseytram Line 2; (iii) the Executive Director (Regeneration) be instructed to formally request, on behalf of the Council, that Merseytravel delay submitting the application for the Line 2 TWAO until there have been further discussions with Merseytravel with a view to resolving a range of in principle concerns including those relating to such matters as funding, alignment and design amongst others; and (iv) in the event that it is not possible to persuade Merseytravel to delay submitting the application for the Line 2 TWAO, a more detailed report be prepared for consideration by Full Council with a view to the Council formally objecting to the application for the Line 2 TWAO with the aim of either: · persuading Merseytravel to propose amendments to the application for the Line 2 TWAO in order to address the Council’s concerns; or · persuading the Secretary of State to amend any Line 2 TWAO which he may be minded to make, so that it addresses the Council’s concerns.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Portfolio: Regeneration Executive Director/Member: Councillor Peter Millea/Charlie Parker Date of Submission: Subject: 15 April 2005 Merseytram Line 2 Report No/Background papers Contact Officer: Tom McCabe EDR/89/05 Ext. 2253410 Executive summary The purpose of this report is to inform Members of a notice received from the Merseyside Passenger Transport Executive (Merseytravel) informing of its intention to apply to the Secretary of State for Transport for an Order under Section 1 of the Transport and Works Act 1992 for powers to construct and operate Merseytram Line 2 (Line 2 TWAO). Although not stated in the notice, Merseytravel will also be applying to the First Secretary of State pursuant to Section 90(2A) of the Town and Country Planning Act 1990 for a planning direction granting the necessary planning permission to construct Merseytram Line 2. Merseytravel intend to submit the application for the Line 2 TWAO by 28 April 2005. In order for the City Council to avoid having to submit an objection to the application for the Line 2 TWAO, requests have been made to Merseytravel to enter into meaningful discussions with Officers, prior to the submission of an application for the Line 2 TWAO, with a view to seeking to agree matters of principle from the outset. Given that it has to date, not been possible to persuade Merseytravel to delay submitting the application for the Line 2 TWAO, the Council may need to protect its position by formally objecting to the Line 2 TWAO application. This may initially be via a holding objection in order that Merseytravel make the necessary amendments to the proposed order or, if this cannot be agreed, a more substantive objection.
Executive Member Director recommendation Councillor Peter Millea/ Charlie Parker
That:
(i) Members reaffirm their in principle support for a three line tram network servicing Liverpool and the surrounding areas;
(ii) Members note receipt of the notification of intention to apply for the Line 2 TWAO under Section 1 of the Transport and Works Act 1992 in order to obtain the necessary powers to construct and operate Merseytram Line 2;
(iii) the Executive Director for Regeneration be instructed to formally request, on behalf of the Council, that Merseytravel delay submitting the application for the Line 2 TWAO until there have been further discussions with Merseytravel with a view to resolving a range of in principle concerns including those relating to such matters as funding, alignment and design amongst others; and
(iv) in the event that it is not possible to persuade Merseytravel to delay submitting the application for the Line 2 TWAO, a more detailed report be prepared for consideration by Full Council with a view to the Council formally objecting to the application for the Line 2 TWAO with the aim of either:
• persuading Merseytravel to propose amendments to the application for the Line 2 TWAO in order to address the Council’s concerns; or
• persuading the Secretary of State to amend any Line 2 TWAO which he may be minded to make, so that it addresses the Council’s concerns. Key Decision Yes Forward Plan No – Appropriate notices will be published in accordance with the constitution Implementation effective from 22 April 2005 Timescale for action Immediate Reason(s) for Recommendation To inform Members of the impending application for the Line 2 TWAO and to agree an appropriate way forward Alternative options to be considered Either persuade Merseytravel to delay making the application or prepare to formally object to the application for the Line 2 TWAO.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.