Resolved that - (i) Liverpool City Council acts as Accountable Body for Objective One ERDF funding in respect of the Wavertree Technology Park phase 2 project; (ii) on the receipt of an offer letter from the Government Office North West that - · authority be granted for the Executive Director (Resources) to accept ERDF grant of up to £1,499,999towards the cost of delivering the project; · the Divisional Manager (Regeneration Programmes) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; · the City Council’s capital programme be adjusted to reflect ERDF expenditure on this project of £519,413 during the financial year 2005/06, £830,587 during 2006/07 and £149,999 during 2007/08 ; and · authority be granted to commit expenditure in order to undertake works that will fulfil the terms of the ERDF offer letter; and (iii) further reports to be submitted to Members as and when appropriate to update on progress.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Liverpool City Council as a key partner in the regeneration of the City, and as Accountable Body for Liverpool Land Development Company (LLDC) must act as the Accountable Body for Objective One ERDF funding for projects initiated and/or delivered by LLDC. The latest scheme requiring agreement to act as Accountable Body is Wavertree Technology Park phase 2, a 3,940 sq mtr speculative office development project to be undertaken at Wavertree Technology Park. Total eligible project cost is £4,600,861 with £1,499,999 ERDF sought from the Eastern Approaches SIA allocation.
2. The project will be delivered by Delma Developments Ltd, supported by the City Council as Accountable Body for the Objective One grant. Delma Developments is an arm of Northern Trust and this is the second development undertaken by Delma at Wavertree, the first being a pre-let 2,000 sq mtr office scheme completed in 2002. The project is included in the Atlantic Gateway SIA Integrated Development Plan.
3. Appendix 1 describes briefly the project, its funding package, timescale for delivery and anticipated outcomes. The project funding comprises funding from Objective One with all of the match funding being provided by the private developers. This report seeks authority for LCC to act as Accountable Body for the Objective One funding. There is no requirement for LCC to provide financial contribution to the project costs but the capital budget will need to be adjusted to reflect the ERDF grant.
Executive Member/Director recommendation. Cllrs Peter Millea/Keith Turner Executive Director for Regeneration, Charlie Parker –
It is recommended that Members approve;
1. Liverpool City Council acts as Accountable Body for Objective One ERDF funding in respect of the Wavertree Technology Park phase 2 project. 2 On the receipt of an offer letter from the Government Office North West that:
(a) Authority be given to the Executive Director Resources to accept ERDF grant of up to £1,499,999 towards the cost of delivering the project.
(b) The Divisional Manager for Regeneration Programmes is appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises.
(c) The City Council’s capital programme be adjusted to reflect ERDF expenditure on this project of £519,413 during the financial year 2005/06, £830,587 during 2006/07 and £149,999 during 2007/08
(d) Authority be given to commit expenditure in order to undertake works that will fulfil the terms of the ERDF offer letter
3. Further reports to be submitted to Members as and when appropriate to update on progress.
Key Decision:
yes
Forward Plan
yes
Implementation effective from: Date of Decision
Timescale for action:
Subject to receipt of an ERDF approval letter the developer is anticipating a start on site in September 2005 with completion before the end of 2006.
Reason(s) for Recommendation:
To seek formal approval for Liverpool City Council to act as Accountable Body for ERDF grant that will allow the project to proceed.
Alternative options to be considered: This is not considered to be an option. Neither Delma nor Northern Trust are able to apply for the ERDF grant and Liverpool City Council has agreed to act as Accountable Body for projects that support LLDC.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.