Resolved
Resolved that the contents of the report submitted be noted and the programme of works identified therein to prepare a New Data Centre at Premier Court at an estimated cost of £800k be agreed.
Executive Board noted this item on Friday 10 June 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the contents of the report submitted be noted and the programme of works identified therein to prepare a New Data Centre at Premier Court at an estimated cost of £800k be agreed.
For some time now it has been recognised that the City Council ICT infrastructure is not adequate to meet the demanding business requirements placed on it now and in the future and officers have been considering options for a more robust reliable and capable ICT infrastructure that will support the Councils requirements and avoid risk to the business.
One of the problems facing the Council is that all the key services are handled in the India Buildings Data Centre which cannot provide the flexibility to expand the infrastructure and take on additional services. In recent months there have been a number of system failures at India Buildings which has caused serious disruption to the councils IT services.
In March 2004 the Executive Member Resources approved a recommendation to provide a data centre following a report by the District Auditor which highlighted the significant risk to the City Council in housing all data and computing services in one location with no full back up facility. A data facility has now been provided in the basement of the Municipal Buildings as a part solution.
That report also stated that a further report would be brought to Members regarding the final relocation from the India Buildings site.
Further options for a second data centre have now been considered by officers from the Premises Management Unit and LDL, The basement of Premier Court has been identified as the preferred option in terms of location and cost effectiveness. Detailed designs to refurbish the space to meet requirements are currently being produced. Capital provision has been made available in the City Councils 2005/06 Capital Programme ( £800k ).
A one off break clause in the lease for the current data centre at India Buildings is available in January 2006.This will enable the council to vacate the premises. It is therefore essential that the proposed new data centre be completed in time to be available to relocate computer operations from the existing premises at India Buildings To enable these tight timescales to be met it is proposed to tender the scheme giving the respective contractors a short period for return of their tender documentation.
It is further proposed to nominate within the tender, specialist sub contractors who carried out the installations to the Municipal Buildings data centre and were selected by competitive tender.
Executive Member/Director recommendation David McElhinney
That the contents of the report are noted and the programme of works identified to prepare a New Data Centre at Premier Court at an estimated cost of £800k is agreed.
Key Decision? Yes
Forward Plan/5 days notice/special urgency
Yes
Implementation effective from 17 June 2005
Timescale for action - Immediate action required to meet the deadline for the vacation of India Buildings.
Reason(s) for Recommendation - To provide a new Data Centre following the vacation of India Buildings by implementing the lease’s break clause
Alternative options considered – Retain existing location, however this is not considered adequate for the councils demanding business requirements.
Consultation - The proposal is the result of joint working between staff from Liverpool Direct Limited and the Premises Management Unit
The estimated cost of works necessary to achieve the refurbishment of an area in the basement of the Premier Court for use as a Data Centre is outlined below: Building Works – demolition, waterproofing, new raised floor
Electrical Works – install new electrical switch room, , UPS installation, electrical infrastructure
Mechanical Works – air conditioning / ventilation equipment
Relocation costs to move IT equipment, new fibre optic links etc
Total = £800k
Best Value:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Data Centre Premier Court (RES/8)Report | 3 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.