BSF -Strategic Business Case (CHS/2)

Agreed Executive 6 papers

Executive Board agreed this item on Friday 10 June 2005. Below is the council's own wording, with the papers it was decided on.

Item4m

Resolved

Resolved that – (i) this initial version of the Strategic Business Case be agreed for submission to the DfES in accordance with the requirements of the Building Schools for Future programme; (ii) the preliminary list of schools to be determined by the BSF Project Board as a priority for inclusion in Wave 2 be also agreed; and (iii) in relation to the Local Education Partnership procurement structure, as confirmed by the Executive Board on 13 May 2005, for delivery of the BSF programme the membership of the BSF Project Board be varied to also include a representative of the Liverpool Archdiocese and Diocese and further an additional Stakeholder Group be established for the Special Educational Needs sector
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Executive summary

The City council is required to produce a Strategic Business Case (SBC) for Building Schools for the Future (BSF). The SBC sets out the context within which schools are operating and the Vision for secondary education. It is important that this document demonstrates the linkage between the delivery of corporate policies and the changes in secondary education which will support these policies. The Vision should demonstrate how the Authority will ensure that the standards of achievement of young people continue to rise and that secondary education engages all young people.

The SBC in particular has tried to ensure that the policies already agreed by the City Council will be more effectively delivered, particularly in relation to inclusion and 14-19 provision. It also considers opportunities for ensuring that schools become effective centres for their local community contributing to creating better social cohesion and effective provision for young people outside the traditional school day.

The SBC at this stage sets out the Principles which should be used to prioritise schools for Wave 2 with work on site starting from April 2007. Schools not included in Wave 2 will be in Waves 4-6 effectively Liverpool schools will all be part of a ten year programme. The priorities for Wave 2 need to be determined by early June and the final option appraisal for deciding which schools to include in Wave 2 will be available for the Executive Board meeting.

The SBC sets out the proposed model for the procurement vehicle for the schools. Following legal advice it appears that neither of the two joint ventures, 2020 or LDL can automatically become the Local Education Partnership (LEP) or part of the LEP without taking part in a competitive procurement process. It appears therefore that the City Council will need to procure a private sector partner for the LEP, although the managed service and infrastructure will be ring fenced fro delivery by LDL as set out in their contract with the City. The SBC is seen as an evolving document and is likely to be modified over time. It is intended to drive the ten year programme. The Executive Board will receive any proposed amendments following each regular six monthly review of the SBC which will be undertaken by the Project Board.

The SBC forms the basis of the Outline Business Case (OBC) which will include more detailed information on the schools in Wave 2 and financial and technical information. Work is already underway which will support the OBC as the timetable for completing this work is again very tight.

Executive Director recommendation: Colin Hilton recommends that –

1. this initial version of the Strategic Business Case be agreed for submission to the DfES in accordance with the requirements of the Building Schools for Future programme; 2. the preliminary list of schools to be determined by the BSF Project Board as a priority for inclusion in Wave 2 be also agreed; and 3. in relation to the Local Education Partnership procurement structure, as confirmed by the Executive Board on 13 May 2005, for delivery of the BSF programme the membership of the BSF Project Board be varied to also include a representative of the Liverpool Archdiocese and Diocese and further an additional Stakeholder Group be established for the Special Educational Needs sector.

Key Decision: Yes

Forward Plan: Yes

Implementation effective from: 17 June 2005

Time-scale for action: The Outline Business Case needs to be produced by 30 September 2005. This will enable the procurement of the private sector parties to form the LEP to proceed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BSF -Strategic Business Case (CHS/2)Report 4 pages DownloadRead as text
PDF
CHS.002 BSF strat bus case: Appendix 1Appendix 2 pages Download
PDF
CHS.002 BSF strat bus case: Appendix 2Appendix 4 pages Download
PDF
CHS.002 BSF strat bus case: Appendix 3Appendix 5 pages Download
PDF
CHS.002 BSF strat bus case: finalReport 113 pages Download
PDF
CHS.002 BSF strat bus case: summaryReport 6 pages Download

At this meeting

Whole meeting

Who was there

13 of 17 attended
MS
Councillor Mike Storey CBEChair, present
DA
Councillor Dave AntrobusMember, apologies
WB
Councillor Warren BradleyMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, apologies
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
RO
Councillor Richard OglethorpeMember, present
KT
Councillor Keith TurnerMember, present
SD
Sir David HenshawOfficer, present
PH
Phil HalsallOfficer, present

All 17 on the meeting page

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open