Resolved that – (i) the final proposal of the Hope Street Public Realm Improvement scheme be approved; (ii) the Executive Director (Regeneration) be authorised to accept a capital grant from NWDA of up to £2,330,000 and from the EIP of up to £460,000 for capital funding for the scheme subject to the receipt of offer letters. The City Council will thereby accept the role of accountable body and ensure that each grant is administered appropriately; and (iii) on receipt of offer letters for capital funding: - · the City Council’s capital programme be adjusted to reflect a revised expenditure profile of £2,720,000 (£2,141,500 NWDA, £448,500 EIP & £130,000 general capital resources) in the financial year 2005/06 and £200,000 (£188,500 NWDA & £11,500 EIP) in 2006/07; · expenditure of up to £2,920,000 be committed; · the City Centre Projects Team Manager be appointed as the nominated officer for monitoring compliance with the terms and conditions of both grants. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and · expenditure on the contract works stages of the project is only incurred after the receipt of confirmation of funding from the relevant bodies upon which this project relies for income and the finalisation of all other relevant documents.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. The purpose of this report is to provide an update on the Hope Street Public Realm Improvement scheme, including the scope, scale and remit of the proposals and final cost estimates.
2. Liverpool City Council together with Liverpool Vision has been working with retained consultants to finalise the detailed design for the public realm improvement project on Hope Street. This Scheme responded to a Key Priority Action identified in Liverpool Vision’s Strategic Regeneration Framework (SRF) in 2000, and was closely guided by a steering group formed for this project.
3. The objective of the scheme is to maximise the quality of the pedestrian environment whilst maintaining vehicular capacity and access. This objective is complementary to actions proposed under the adjacent Canning Street Controlled Parking Zone. Executive Board Report No. EDR/260/03 outlined key features of the scheme.
4. Sketch proposal for the scheme received approval from the Environment Working Group (EWG) and funding has been secured from NWDA to enable detailed design of the scheme to take place. The detailed design has allowed preparation of an accurate cost estimate for the scheme and enabled an application to be submitted to NWDA for the implementation of the scheme.
5. Executive Board report EDR/355/04 (7 January 2005) gained approval to accept funding, to commit expenditure based on costs estimated from the detailed scheme design and to include the scheme in the capital programme. The works will be delivered under the City Centre Movement Strategy (CCMS) Framework Contract, and the ‘Contract Negotiation Stage’ was ongoing at the time that the report was submitted. Due to the abnormally large number of negotiated tender items and RPI increases, the target cost for the project exceeds the cost estimate. In particular the cost of Yorkstone has risen considerably together with the percentage of items which the supplier considers will have to be hand finished by a stonemason. The cost of the lamp columns has also risen considerably because of the increase in steel prices.
6. A revised application to NWDA for the capital cost of implementing the scheme which included the target cost was submitted for appraisal in February 2005. Appraisal of the application is now in progress, and a decision is expected in early June 2005.
7. A complementary application has been submitted for funding of £460,000 from the Environmental Improvement Programme (EIP) for the enhanced design of the new area of public realm at the junction of Hope Street and Mount Street.
8. The final element of funding for the scheme (£130,000) is specifically for traffic signal improvements and will now be included in the Highways Capital Programme in the 2005/06 financial year. The Highways Manager will ensure that this scheme is financed from available Transport Services capital resources for 2005/06.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.