The 2004/05 Local Transport Plan Annual Progress Report (APR) (REG/14)

Noted Executive 1 paper

Executive Board noted this item on Friday 24 June 2005. Below is the council's own wording, with the papers it was decided on.

Item14a

Resolved

Resolved that the 2004/05 Local Transport Plan Annual Progress Report (APR), as submitted, be noted.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 5 pages

Executive summary

Background

1.1The first Local Transport Plan (LTP) is now in its final year of delivery and continues to identify, fund and deliver integrated transport solutions to tackle social, economic and environmental issues across Merseyside.

1.2Annual Progress Reports (APRs) are required each year by the Department for Transport (DfT) as a means of reporting on progress of the LTP. APRs do not constitute new transport strategies or funding packages. The second (provisional) LTP (the subject of separate reports) will set out the provisional strategy for the next 10 years and will be submitted to DfT at the end of July 2005.

1.3The APR for submission this year covers the 2004/05 financial year. DfT is strongly encouraging authorities to submit their APRs at the end of June, as opposed to the end of July, in order to allow time for DfT to address any issues of conflict or ambiguity within the submission ahead of its final assessment.

1.4This year’s APR is also required to be a short, simple document aimed at conveying technical information in graphical and tabular format. It focuses on the following:

• Progress towards targets and objectives • Scheme delivery and LTP spending (including maintenance data) • Progress on major schemes

1.5As in previous years, Merseyside’s Strategic Transportation and Planning Committee (MSTPC) will be requested to consider the APR. However the APR needs to be fully approved by each of the partners. 2 Key messages from LCC contained within the APR

2.1The APR builds on the success of last year’s report, which was received favourably by the Government. Work has continued on delivering the strategy, including work on the major schemes.

Spend and delivery

2.2In the 2004 APR, LCC committed itself to a capital programme of £15.185m which was increased to £15.340m to cover integrated transport and maintenance. £15.121m has been spent on transport schemes and the slight underspend of £219K has been carried forward into the 2005/06 capital programme to fund Park Road Improvement scheme.

2.3All supplementary funding awarded for the development of the Strategic Investment Areas (£2.149m) and the City Centre Movement Strategy (£1 million) was spent on appropriate works within these areas.

2.4Looking at delivery on the ground and at divergence between projected delivery and actual delivery (an area of particular interest to the DfT) then progress can be exemplified as follows:

• Cycle tracks, lanes and advance stop lines – delivery exceeds forecasts, aided by match funding from Sustrans and the integration of cycling infrastructure with other programme areas. • New or improved footways – apparent under-delivery but this is due to an error in the way that the figure was forecast in 2004. • School travel plans – delivery exceeds forecasts, reflecting the success of the School Travel Co-ordinator bursaries and School Capital Grants. • Toucan / puffin crossings – LCC have implemented more crossings than forecast in the 04 APR. This is due to greater focus in this area.

Performance targets

2.5This year’s APR will emphasis the good progress which has been made towards many of the LTP’s performance indicators. For the majority of performance indicators, the partners appear to be on target.

Major schemes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The 2004/05 Local Transport Plan Annual Progress Report (APR) (REG/14)Report 5 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 22 attended
MS
Councillor Mike Storey CBEChair, present
DA
Councillor Dave AntrobusMember, present
WB
Councillor Warren BradleyMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, apologies
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
RO
Councillor Richard OglethorpeMember, present
KT
Councillor Keith TurnerMember, apologies
SD
Sir David HenshawOfficer, present
PH
Phil HalsallOfficer, present

All 22 on the meeting page

On this subject at Liverpool

Search all
  1. The 2004/05 Local Transport Plan Annual Progress Report (APR) (REG/14)This decision
  2. Local Sustainable Transport Fund City Cycle Hire Scheme - Procurement Approval (TCC/11)Approved
  3. Local Sustainable Transport Fund UpdateAgreed
  4. Key Issues arising from Local Transport White Paper.Agreed
  5. Update on joint working between Local Transport Plan and Local Development FrameworksNoted
  6. Presentation - Local TransportAgreed

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open