Declaration of Princes Park Renewal Area (HSG/9)

Approved Executive 2 papers

Executive Board approved this item on Friday 8 July 2005. Below is the council's own wording, with the papers it was decided on.

Item20u

Resolved

The Board considered a recommendation that- (i) the contents of the report submitted be accepted subject to the exclusion of the demolition proposals in Section 6 (Welsh Streets (Part)) for the area between and including Powis Street and Admiral Street; (ii) all relevant representations or comments reported to the Executive Board following the Notice of Intention to declare the Renewal Area, be considered; (iii) the Princes Park area be declared to be a ‘Renewal Area’ within the meaning of the Local Government and Housing Act 1989 as amended by the Regulatory Reform (Housing Assistance) (England and Wales) Order 2002 for a 10 year term (2005-2015); (iv) the Executive Director (Regeneration) be authorised to work with public and private sector partners to prepare a three year delivery plan that reflects the guidance provided by ODPM for Members approval; (v) the Executive Board is prepared, in principle, to consider the making of Compulsory Purchase Orders if it proves necessary to do so to facilitate the renewal of the area; and (vi) a further report be produced by Officers to identify the delivery programme necessary to deliver the proposals, and seek approval for the programme. _____ The Board were advised that at its meeting on 6 July the Three Parks Neighbourhood Committee agreed to ask the Executive Board not to declare the renewal area without also agreeing an amended clearance zone in respect of the Welsh Streets and that in the event they decided to declare the Renewal Area without the amended clearance zone the Board should ask that the matter is referred to City Council for consideration. _____ Resolved that the recommendation be approved.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 12 pages

Executive summary

The purpose of this report is to advise the City Council of the outcome of the Neighbourhood Renewal Assessment (NRA) undertaken in the Princes Park area as depicted on the map attached as Appendix 2 and to seek City Council support to declare this area as the Princes Park Renewal Area.

2. Historical Context and Community Involvement

The Princes Park area is located within the “Inner Core” and lies within the City Centre South Housing Market Renewal Initiative (HMRI) boundary. It is contained within the Princes Park and Riverside Wards and comprises a number of neighbourhoods defined by existing resident group boundaries. There are approximately 3000 dwellings contained within 2653 properties within the area.

The area is a mix of larger properties on the arterial routes with a mix of smaller Victorian and more recent local authority and RSL infill properties in the smaller side streets. The frontage properties in Devonshire, Belvidere and Princes Roads are within the Princes Road Conservation Area. The Victorian estates in the proposed area have been included in housing regeneration programmes in the 1970’s and early 1980’s resulting in the improvement of many properties and these programmes extended the sustainability of the neighbourhood.

The area has a high Black and Minority Ethnic population with 76.2% of the Liverpool total being concentrated in the five old wards, Abercromby, Arundel, Picton, Smithdown & Granby.

The City Council has adopted a Neighbourhood Management model (INclude) in the Dingle area which it is intended to extend to the rest of South Central Neighbourhood.

The INclude Housing & Environmental Delivery Plan 2002 – 2007 set out a programme for the development of Neighbourhood Plans. Neighbourhood Planning Groups were established in 2002 in the Welsh Streets and Camelot Neighbourhood, and these groups have developed a Community Plan for regeneration. Part of the remit of the Neighbourhood Renewal Assessment was to review and evaluate these emerging plans.

More recently, a separate group has formed called the Welsh Street Home group, and whilst they have been a vocal lobby against the clearance proposals, they have not previously been actively involved in the Neighbourhood Planning process. Their disagreement with the emerging clearance proposals is well recorded.

3. The Neighbourhood Renewal Process

In February 2004 Pennington Consultancy, an independent company appointed by the Council with community involvement, were commissioned to undertake a Neighbourhood Renewal Assessment (NRA), which is a required part of the process when considering the declaration of a Renewal Area. The purpose of the NRA was to identify options for this housing priority area, identified in the HMRI Prospectus as an area appropriate to target investment and provide the opportunity to create a more sustainable housing market.

As previously mentioned, the brief to Pennington’s was that the NRA should review and build on the work already undertaken with the Welsh Streets Neighbourhood planning process, started in 2002 and the Camelot Neighbourhood Planning process started in 2003.

The NRA included a survey of the condition of the properties and a detailed questionnaire to establish the socio economic circumstances of residents, in order to generate and evaluate various options.

4. Key Physical and Socio Economic Findings of the NRA

Deprivation Index

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Declaration of Princes Park Renewal Area (HSG/9)Report 12 pages DownloadRead as text
PDF
HSG.9: Declaration of Princes Park Renewal Area: AppendixAppendix 10 pages Download

At this meeting

Whole meeting
19Minutes of the Last MeetingApproved 20aE-Government Schemes (RES/12)Agreed 20bLand at eastern end of Tynwald Hill (RES/13)Agreed 20cLiverpool Architectural Design Trust (RES/14)Decided 20dTrident House, Derby Road (RES/15)Approved 20eShip and Mitre Public House, Dale Street (RES/16)Agreed 20f72, 78 and 80 Mulgrave Street (RES/17)Agreed 20gProgress report on the further integration of mental health and drugs/alcohol services within Mersey Care NHS Trust.(HSG/10)Agreed 20hService Level Agreement with Liverpool Housing Trust, Mental Health Services (HSG/11)Agreed 20iODPM Capital Funding 2004/05. Proposed improvement works to Direct Access Centres.(HSG/12)Agreed 20jEducation Capital Programme June 2005 (CHS/3)Approved 20kSurplus School Sites (CHS/4)Approved 20lFountains Children’s Centre/ Melrose Sure Start Local Programme (CHS/5)Approved 20mWalton Children’s Centre (CHS/6)On the agenda 20nOperational Forums and Problem Solving at a Neighbourhood Level (NM/2)Approved 20oEnforcement Review (NM/3)Approved 20pLocal Nature Reserve Designation (GI/4)Decided 20qDraft City Centre Parking Strategy – Making Liverpool More Business and Visitor Friendly (REG/16)Decided 20rStatement of Accounts 2004/05 (RES/18)Noted 20sNew Housing Development Supplementary Planning Document (REG/9)Approved 20tDeclaration of Picton Renewal Area (HSG/8)Approved
20uDeclaration of Princes Park Renewal Area (HSG/9)This decision
21Social Care and Health Select Committee - 16 June 2005 - Supported Bedsits (HSG/48)Decided

On this subject at Liverpool

Search all
  1. Declaration of Princes Park Renewal Area (HSG/9)This decision
  2. Declaration of Princes Park Renewal Area (HSG/9) - Housing and Community Safety Select Committee - 8 September 2005Approved
  3. Declaration of Princes Park Renewal AreaApproved
  4. Declaration of Princes Park Renewal Area (HSG/9)Deferred

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open