Resolved that – (i) authority be given to increase the authorised expenditure on the contract for phase 4 of the works at Alsop High School to £2,375,000 and to increase the budget by £75,000 to be financed by the school; (ii) a budget of £530,000 be established to fund the cost of the construction of a new boundary wall at Alsop High School to be financed from: · £137,000 school’s formula capital contribution; and · £393,000 from the balance of Planned Maintenance for 2005/06; (iii) authority be given to increase the authorised expenditure on the contract for phase 2 of the new dance and fitness suite at Childwall comprehensive to £337,000 and to increase the approved budget by £23,000 to be financed by the school; (iv) a budget of £35,000 is established from the balance of Planned Maintenance for 2005/06 to fund the refurbishment of the infants classrooms and roofing works at Mosspits Infants; (v) a budget of £300,000 be established form the balance of Planned Maintenance for 2005/06 to fund a scheme of window replacement at 6 primary schools; (vi) a budget allocation of £150,000 is added to the NRF schools security funding from the balance of Modernisation Funding (All Schools) for 2005/06; and (vii) the allocations of School’s Access Initiative Funding to the schools set out in the report be noted.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to seek authority to commit resources from specific Education Capital allocations for 2005/06 to projects identified below.
1. Current Position
The Executive Board of 1st April 2005 approved the allocation of resources from specific Education capital allocations for 2005/06 towards a number of new projects. Following the approval of the Council’s Capital Programme for 2005/06 on 27 April the following balances of the annual formulaic capital allocations, which the Authority can use to deliver its strategic building priorities for schools, remain uncommitted:
1. Comprises an allocation for 2005/06 of £545,306 plus un-committed resources from 2004/05 of £351,029
2. Project Proposals
• Alsop High School, Phase 4 - the current phase of development at the school comprising a two storey teaching block is nearing completion. The re-designation of the block as an IT facility after construction commenced required changes to the design such as the installation of air conditioning. Increased costs of £75,000 have been incurred which are to be met by the school. Authority is therefore sought to increase the authorised expenditure on the contract to £2,375,000. • Alsop High School, Boundary Wall – a section of the sandstone wall at the school was demolished in January following a partial collapse before Christmas. Planning approval has recently been granted for the construction of a new sandstone wall with railings. It is therefore recommended that a budget of £530,000 including fees and on costs is established to be financed by:
o £137,000 school’s formula capital contribution o £393,000 from the balance of Planned Maintenance for 2005/06
• Childwall Comprehensive – Phase 2 of a new dance and fitness facility at the school has recently been completed. Unforeseen increased costs of £23,000 are forecast upon settlement of the final account to be met by the school. Authority is sought to increase authorised expenditure to £337,000.
• Mosspits Infants – a series of ongoing leaks at the school following roofing works several years ago has resulted in significant deterioration of the plasterwork in the infant’s classes and corridor. The leaks have now been rectified and it is proposed to refurbish the infant’s classes during the summer break. Additional works to replace to smaller areas of flat roof are also proposed. It is recommended that a budget of £35,000 is established to fund works, 20:20 fees and on costs from the balance of Planned Maintenance for 2005/06.
• Window Replacements – As part of the ongoing programme of planned maintenance a scheme of window replacements is recommended at the following schools:
o Blackmoor Park Infants – rear wing incorporating the hall o New Park Primary – rear elevation estimated o Sudley Juniors – rear elevation and remaining metal windows on front elevation. o Clifford Holroyde – rear elevation o Croxteth Primary – Infants wing o Smithdown Primary – front elevation.
It is recommended that a budget of £300,000 be established from the balance of Planned Maintenance for 2005/06 to fund the works, professional fees and on costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.