Resolved that – (i) Liverpool City Council acts as Accountable Body for the ODPM grant in respect of the Men’s and Women’s Direct Access Centres; (ii) On receipt of an offer letter from the ODPM - · authority be granted for the Executive Director (Supported Living and Community Safety) to accept an ODPM grant of up to £1.350 million for the Men’s DAC and £1.115 million for the Women’s DAC; · the Manager (Supported Living in Neighbourhoods) be appointed as the nominated officer for monitoring compliance with terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year the liability arises; and · the schemes be moved from the Social Services to the Housing (HRA) Capital Programme in 2005/2006 and 2006/7; (iii) a fully costed proposal for the Men’s and Women’s DACs be prepared; and (iv) subject to the receipt of a capital offer letter from the ODPM, the agreement of the Executive Directors (Supported Living and Community Safety) and (Resources) that the proposals are affordable given the availability of capital grant and on-gong revenue resources, then the expenditure be committed.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. In 2003, the City Council submitted its Homelessness Strategy to the Office of the Deputy Prime Minister (ODPM). The report was well received and identified a number of key recommendations. Included in these were a series of proposals to improve the condition of accommodation for homeless people in the city. Accordingly a bid was prepared, in line with ODPM guidelines, for capital funding to carry out a series of improvement works. Included in the bid were the following proposals: £000s i. Improvements to Men’s Direct Access Centre 1,350 ii. Improvements to Women’s Direct Access Centre 1,115
2. Single people who find themselves homeless in the city are required to present at either Men’s or Women’s DAC in order that staff can carry out an assessment of their homelessness. If it is found that the city has a duty towards the individual they will, where possible, be found temporary accommodation in the DAC. Where this is not possible, staff will attempt to locate other accommodation for clients provided by one of the many agencies in the city who provide a service to single homeless people.
3. The existing Men’s Direct Access Centre, although well placed geographically in the Tuebrook area of the city, is in poor physical condition. It consists of 21 individual rooms of temporary accommodation. Residents share communal facilities such as the TV lounge, kitchen and bathrooms. The hostel has almost 100% occupancy rates. The refurbishment will include renovating the property to include en suite facilities where possible and to improve communal areas. These will provide residents with more appropriate facilities and will help to provide a more specialist service to homeless people.
4. The Women’s DAC similarly provides temporary accommodation for 21 single homeless women. They also share communal facilities such as TV lounge , kitchen and bathrooms. The proposal is to provide more self contained units with en-suite facilities providing privacy and protection for vulnerable single women. Although conditions there are better than at MDAC, the building still requires significant refurbishment. As in the MDAC there is 100% occupancy and high demand for placements. Full specifications will be worked up as soon as possible after this report is approved in order that the works can progress to the next stage.
5. The ODPM Capital Grant is provided on the basis that there will be no additional grant from ODPM to deal with running or support costs.
6. It is proposed that on approval of this report staff from Enterprise Liverpool, in conjunction with staff and residents, begin discussions to identify what works are required to draw up draft proposals within the limits of the funding available.
1. Liverpool City Council acts as Accountable Body for the ODPM grant in respect of the Men’s and Women’s Direct Access Centres;
2. On receipt of an offer letter from the ODPM: a. authority be granted for the Executive Director (Supported Living and Community Safety) to accept an ODPM grant of up to £1.350 million for the Men’s DAC and £1.115 million for the Women’s DAC; b. the Manager (Supported Living in Neighbourhoods) be appointed as the nominated officer for monitoring compliance with terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year the liability arises; c. the schemes be moved from the Social Services to the Housing (HRA) Capital Programme in 2005/2006 and 2006/7; and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.