Church Street Phase 2 (REG/33)

Decided Executive 1 paper

Executive Board decided this item on Friday 2 September 2005. Below is the council's own wording, with the papers it was decided on.

Item45h

Resolved

Resolved that on receipt of an offer letter from the Northwest Development Agency, the Executive Director (Regeneration) be authorised to - (i) accept a grant from the Northwest Development Agency, up to a maximum of £450,000 for the Church Street Phase 2 project in the financial year 2005/6; (ii) adjust the City Council’s Transportation Capital Programme to reflect expenditure and grant income against Church Street Phase 2 to a maximum of £450,000 within the financial year 2005/6; (iii) appoint the Divisional Manager (Highways and Environment) as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; and (iv) commit expenditure up to a maximum of £450,000 on the Church Street Phase 2 project.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 6 pages

Executive summary

Church Street is one of the remaining significant CCMS public realm projects to be delivered before 2008. The project is vital to create a high quality environment in the heart of the city centre retail area.

The scheme will link together the Church Street corridor with the Package X public realm project (in Greater Williamson Square and the Cavern Quarter) and the proposed public realm to be delivered through the PSDA project to create a world class environment for the combined retail quarter.

The project is being delivered in three principal phases: Phase 1: Concept Design Phase 2: Detailed Design and Contract Preparation Phase 3: Construction

As Members will recall, the Phase 1 project was undertaken by 2020 Liverpool and BDP and proposed an overall design theme called ‘The Ribbons of Life’. The ‘ribbons’ represent social, economic and cultural aspects of Liverpool and its people and are integrated into the design through the surfacing, street furniture and sculptural elements of the project.

The concept design proposal includes high quality granite surfacing on concrete foundations, street lighting that can accommodate banners and Christmas decorations, bespoke street furniture that rise from the surfacing, new tree planting and, through the appointment of the artist Danny Lane, sculptural elements along the street.

Phase 1 was undertaken between February and May 2005. It cost a total of £95,000 of which £65,000 was incurred in 2004/05 and £30,000 in 2005/06 and was financed through an SRB6 grant.

Extensive consultation on the proposals has been carried out throughout the design process and the scheme now needs to be taken forward into Phase 2 to mobilise detail design. This report seeks Member approval to accept an NWDA grant and commit expenditure to deliver Phase 2 of the project.

Phase 2 will require a further design brief to be issued to 2o2o Liverpool to undertake this commission. The sub-consultancy agreement with BDP will be extended to carry out the urban design services with 2020 leading on all engineering and cost management services.

Phase 2 project will include the following tasks:

ƒ A public exhibition based on the concept design to date.

ƒ The preparation of detail design for all project components.

ƒ Consultation with relevant departments, maintenance partners, Members and key stakeholders on the detail design.

ƒ Preparation and facilitation of traffic orders in relation to the scheme.

ƒ Installation of a trial panel to review the paving design.

ƒ Preparation of contract information for issue to one of the CCMS Framework Contractors.

ƒ Development of a robust project cost, programme and works package with the appointed contractor in preparation of contract award.

ƒ Submission of funding applications and project information to the funding agencies for appraisal in relation to grant for Phase 3.

Once this detail design stage is complete, the project will be in a position to move forward to Phase 3 (Construction) subject to the award of further funding. This report does not however seek authority to accept grant or commit expenditure other than the NWDA grant to deliver Phase 2.

Executive Member/Director recommendation: (Councillors Peter Millea and Keith Turner/Charlie Parker)

On receipt of an offer letter from the Northwest Development Agency, the Executive Director of Regeneration (Charlie Parker) be authorised to:

1. Accept a grant from the Northwest Development Agency, up to a maximum of £450,000 for the Church Street Phase 2 project in the financial year 2005/6.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Church Street Phase 2 (REG/33)Report 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Church Street Phase 2 (REG/33)This decision
  2. St James Methodist Church, High Street, Woolton Village, Liverpool L25 7TE (Woolton Ward)Approved
  3. Former George Henry Lee Building, 51-57 Church Street, Liverpool L1 3AY (Central Ward)Approved
  4. 1-5 Church Street, Liverpool, L1 1DA (Central Ward)Approved
  5. Tree Preservation Order 384 (2009) - Land at St. James Methodist Church, High Street, Liverpool 25 (Woolton Ward)Decided
  6. Central Ward - TRO for Church Street / Lord St areaApproved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies