Resolved that - (i) the selection of a fourth Framework Contractor ( Birse Civils Limited) for the CCMS works be approved, given that all procurement and legal issues have been addressed in accordance with Council Policy and Standing Orders. Individual submissions will be made for each Task Order providing further detail on the budgets and timescale for completion of each; and (ii) the Framework Contract as described be entered into with Birse Civils Limited with immediate effect. This will not bind the Council to order any amounts of work from the Framework Contract or to receive or pay for any amounts other than that contained in subsequent Task Orders.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
I. To advise Members of the current status regarding the procurement of a suitable additional Contractor to assist with carrying out the City Centre Movement Strategy works.
II. To seek Executive Board authority for the scheme in order that the City Solicitor can enter into an Agreement with the recommended Contractor for signature as a Deed.
Background
2.1A briefing note was submitted to the Joint Executive Members on 16 September 2003 that provided a background to the CCMS Framework Contract procedure.
2.2Following tendering and evaluation, Executive Board approval was obtained for three Contractors namely Prismo (Jarvis), Aggregate Industries (Kennedy) and Balfour Beatty at the Board meeting on Friday 16th April 2004.
2.3Due to the financial situation of one of the three contractors, namely Prismo (Jarvis) it is now recommended that a fourth Contractor should be added to the list to safeguard the integrity of the framework.
3 Project Update
(a) Programme Update
3.1The three Contractors named above were selected to carry out the work in the CCMS programme.
3.2Following selection, the first three Task Orders were allocated as follows:
Hunter Street/Byrom Street Prismo Highways Renshaw Street/Berry Street Balfour Beatty Hope Street Kennedy Asphalt
Prismo faced financial difficulties just prior to signing the Agreement for the Hunter Street / Byrom Street scheme and Kennedy Asphalt were asked at short notice to price the Task Order and prepare to start the work. This contract is now complete and Kennedy have started work on their next scheme on Tithebarn Street. Hope Street has just had funding approval and work commenced in August 2005. Balfour Beatty are progressing Renshaw Street/Berry Street and are also progressing work on Seymour St / Copperas Hill which is a closely related scheme.
3.3The three previously unsuccessful Contractors and the three others who did not reach the short list, but who reached the last nine list, were invited to submit tenders based on similar tender documentation to that used in the previous contract. The main difference between them was, that a more realistic generic scheme could be used for the contractors to price for comparison purposes based on cost. Tender appraisal was based on 40% quality and 60% price.
3.4Tenders were evaluated on both quality and price by the assessment team within Highways Management and in collaboration with the LCC Procurement Unit. The successful contractor has now been provisionally nominated and is:
Birse Civils Limited
3.5Subject to the approval of this report and acceptance of an offer letter, LCC will be able to enter into an Agreement with Birse Civils Ltd.
There is no guarantee of any work at this stage, although a list of potential CCMS schemes was presented in the contract documents. This list included:-
Strand Corridor Improvements Church St/Lord St Improvements Hall Lane Improvement
In addition to these, there are CCMS Package 2 works and the reversal of Skelhorne Street including rationalisation of Elliot Street junction.
A separate report and submission will be prepared for each of these Task Orders as part of any scheme approval process. 4 Maintenance and Management Mechanisms
4.1All the streets in the CCMS Framework are within the adopted highway and will therefore continue to be maintained by Enterprise-Liverpool (E- L) under the current highways maintenance agreement.
Executive Member/Director recommendation (Councillors Peter Millea and Keith Turner/Charlie Parker)
That;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.