Resolved that – (i) the contents of the progress report submitted, be noted; (ii) the Council confirms a commitment to carry out a major redevelopment of the Colomendy site at an estimated cost of £10.1 million (at December 2006 price base) subject to - · that Kingswood produce a satisfactory business plan for the future redevelopment of the centre; · that Kingswood achieve the targets set out in the proposed three-year Initial Services Phase Agreement; and · that the Schools Forum agrees to top-slice the Schools Budget by £500,000 to provide for the revenue contribution. (The schools, as part of the agreement with Kingswood will receive subsidised places for all Liverpool children and enhanced subsidy for those children who are from families on low income and this will continue in the enhanced provision.); (iii) tenders be invited for the NOF approved works for new and improved outdoor adventure facilities and that these works be allowed to proceed subject to the approval of Big Lottery; and (iv) the Council enters into an “Initial Services Phase Agreement” with the preferred operator to operate the site from October 2005 for a period of three years. Terms and conditions to be settled by the Executive Director in conjunction with the City Solicitor.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
CITY STATUS – PUBLIC CHS/12 Portfolios: Executive Members: Children’s Services / Resources Cllr Paul Clein / Cllr Keith Turner
Date of submission: Subject: Redevelopment of 15 / 17 August 2005 Colomendy Centre for Outdoor Education Report No. DE/07/05 Contact officer: Ken McCandless Background papers: DE/102/03, Ext: 233 8222 DE/53/04 Colomendy Hall Development Study.
Executive summary: The purpose of this report is to:
a) Update Members on the current situation with regard to the proposed redevelopment of the Colomendy Centre for Outdoor Education b) Confirm a commitment to carry out a major redevelopment of the site at an estimated cost of £10.1 million (at December 2006 price base) subject to corporate considerations over the level of borrowing for capital purposes and its effect on the Capital Programme and Council Tax and subject to the following conditions: i) that Kingswood produce a satisfactory business plan for the future development of the centre. ii) that Kingswood achieve the targets set out in the proposed three- year Initial Services Phase Agreement iii) that the Schools Forum agrees to top-slice the Schools Budget by £500,000 to provide for the revenue contribution. (The schools, as part of the agreement with Kingswood will receive subsidised places for all Liverpool children and enhanced subsidy for those children who are from families on low income and this will continue in the enhanced provision.) c) Subject to the above commitment to approve the seeking of tenders now for new and improved outdoor adventure facilities at an estimated cost of £1,060,000 (at current prices) financed by a £780,000 NOF lottery grant that has been approved for this purpose and must be spent by 31 March 2006, and a Council contribution of £280,000 from the earmarked reserve for the Colomendy centre. d) Subject to the above to enter an Initial Services Phase Agreement with the preferred operator (Kingswood) for them to operate the Centre and for them to carry out sufficient minor redecoration and refurbishment using their own funds to enable continued use of the Centre until such time as the full refurbishment is carried out. Members may recall from previous reports about the Colomendy Centre that the buildings on the site are in extremely poor state of repair and decoration, require new furnishings and do not meet the needs of current customers. As a result of this, together with continued speculation about a major refurbishment scheme, the Centre now attracts very few customers. The Centre currently makes a deficit in the region of £1 million per year even though staffing has already been reduced significantly.
To date no contracts have been signed nor has any redevelopment works begun. However, substantial progress has been made both in terms of design development and also operational planning. In taking the project forward the design team has worked closely with the preferred operator, Kingswood, and the local Planning Authority.
In terms of design development, the current situation is: a) All planning permissions for the major redevelopment and the outdoor adventure facilities are now in place. b) Planning conditions necessary before any works begin are being actioned (e.g. licenses in connection with any proposed working that could affect great crested newts, lesser horseshoe bats and badgers that currently occupy the site). c) An Environmental Impact Assessment has been undertaken and provided to the planning authority. d) An application has been made to obtain a public footpath diversion order for which planning permission has already been obtained. e) A design freeze is in place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.