Resolved

Resolved that – (i) the proposed works be included in the City Council Capital programme to enable funding of £426,000 to be drawn down from the ODPM Homelessness Directorate; (ii) Liverpool City Council acts as Accountable Body for the ODPM grant in respect of the works identified in the report; (iii) on receipt of an offer letter from the ODPM – (a) authority be granted for the Executive Director (Supported Living and Community Safety) to accept an ODPM grant of up to £366,000 for Shaw Street hostel and £60,000 and for improved facilities to single men’s hostels; (b) the Manager (Supported Living in Neighbourhoods) be appointed as the nominated officer for monitoring compliance with terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year the liability arises; (c) the schemes be moved from the Social Services to the Housing (HRA) Capital Programme in 2005/2006 and 2006/7; and (iv) subject to the receipt of a capital offer letter from the ODPM, the agreement of the Executive Directors for Supported Living and Resources that the proposals are affordable given the availability of capital grant and on-gong revenue resources, then the expenditure is committed.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 3 pages

Executive summary

1. In 2003, the City Council submitted its Homelessness Strategy to the Office of the Deputy Prime Minister (ODPM). The report was well received and identified a number of key recommendations. Included in these were a series of proposals to improve the condition of accommodation for homeless people in the city. Accordingly a bid was prepared, in line with ODPM guidelines, for capital funding to carry out a series of improvement works. Included in the bid were the following proposals: £000s a. Improvements to Shaw Street Hostel 366 b. Improvements to existing facilities at Men’s Hostels 60

This funding is in addition to the £2.4 million which has already been approved for improvement works to the Men’s and Women’s Direct Access Centres.

2. The premises at Shaw Street are managed by Novas-Ouvertures which is a large organisation with interests not only in Liverpool but across the country and in Europe. It provides housing and support for a range of vulnerable people. It is one of the City Council’s many partnerships with external agencies under the Supporting People funding arrangements.The City Council’s role is that of acting as a conduit between ODPM and Novas in order to draw down the funding.

3. The existing 28 bed spaces at the Shaw Street hostel will be converted into 19 self contained flats. The refurbishment will include communal areas providing support services for residents and non-residents. The new facilities will provide a more specialist service to homeless people with mental health and support needs on a self catering basis.

4. The second proposal is to provide facilities in two hostels for homeless men which will provide a warm and comfortable place for a vulnerable client group which would otherwise spend time on the streets. The clients are multi excluded men, often rough sleepers and some with mental health problems. Many of them are heavy drinkers and these facilities will enable residents to have a secure and accessible facility which can be monitored and kept clean. This project is well supported by ODPM advisors.

5. The ODPM requires the City Council to draw down the funding for these elements of the bid before the end of the financial year and it is therefore important that they are formally included in the Capital Programme. The works can then proceed with completion in 2005/6.

Executive Member/Director recommendation (Flo Clucas, OBE/Tony Hunter): That:

1. The proposed works be included in the City Council Capital programme to enable funding of £426,000 to be drawn down from the ODPM Homelessness Directorate.

2. Liverpool City Council acts as Accountable Body for the ODPM grant in respect of the works identified in the report;

3. On receipt of an offer letter from the ODPM: a. authority be granted for the Executive Director (Supported Living and Community Safety) to accept an ODPM grant of up to £366,000 for Shaw Street hostel and £60,000 and for improved facilities to single men’s hostels;

b. the Manager (Supported Living in Neighbourhoods) be appointed as the nominated officer for monitoring compliance with terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year the liability arises;

c. the schemes be moved from the Social Services to the Housing (HRA) Capital Programme in 2005/2006 and 2006/7; and

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ODPM Homelessness Capital Grant Funding 2004/05 (HSG/23)Report 3 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 24 attended
MS
Councillor Mike Storey CBEChair, present
DA
Councillor Dave AntrobusMember, present
WB
Councillor Warren BradleyMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
RO
Councillor Richard OglethorpeMember, present
KT
Councillor Keith TurnerMember, present
SD
Sir David HenshawOfficer, present
PH
Phil HalsallOfficer, apologies

All 24 on the meeting page

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies