Resolved
Resolved that – (i) approval be given to the closure of Heather Court Liverpool 4 and decant status be awarded to the tenants; and (ii) the future use of the building/site will be discussed with the HMRI Team.
Executive Board approved this item on Friday 16 September 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that – (i) approval be given to the closure of Heather Court Liverpool 4 and decant status be awarded to the tenants; and (ii) the future use of the building/site will be discussed with the HMRI Team.
1. Heather Court Sheltered Housing Scheme is situated In Tetlow Street near to County Road, Liverpool 4.
2. The scheme comprises of 41 units of accommodation, 30 bed sits, 10 one bed-roomed flats, and a three bedroom house for the scheme manager.
3. Currently 14 units are occupied and 27 are vacant.
4. The scheme has been identified as not fit for purpose by the Older Person’s Accommodation Strategy Report. The scheme does not provide good quality self contained flats. Tenants share communal baths and showers
5. Due to low demand for flats in the scheme, the scheme has a high percentage of vacancies. Anti social behaviour in the area has resulted in the remaining tenants feeling increasingly vulnerable. Early closure and the re-housing of tenants to suitable alternative accommodation are therefore considered to be the only appropriate option.
Executive Member/Director recommendation Councillor Flo Clucas OBE/Tony Hunter
That -
(i) approval be given to the closure of Heather Court Liverpool 4 and decant status be awarded to the tenants; and (ii) the future use of the building/site will be discussed with the HMRI Team.
Key Decision: No
Forward Plan
Not applicable
Implementation effective from:
23 September 2005
Timescale for action:
On approval of the recommendations, the decant of tenants can begin. The decant process is likely to take approximately 8 months to complete.
Reason(s) for Recommendation:
The property has been identified as not fit for purpose by the Older Person’s Accommodation Strategy Report and refurbishment is considered not to be cost effective or desirable.
Refurbishment of the scheme has been evaluated and has found not to be cost effective. Consultation will take place with the H.M.R.I Team to discuss future use of the building/site linking with the overall plans for the area.
Following the recommendation of the Older Person’s Accommodation Strategy that Heather Court was not fit for purpose, consultation took place at a meeting with tenants and their families.
The meeting was held in February 2005 where the future of the scheme was discussed and the reasons for its proposed closure debated.
The Neighbourhood Manager for the North Liverpool Team has been consulted and supports the proposal to close the scheme. Ward Councillors for the area have been advised of the proposal to close the scheme
The financial implications of the decision to close Heather Court (assuming decanting starting in July 2005 and is completed by April 2006 are summarised below :-
Year General Fund(£) HRA(£) Capital(£)
2005/06 2,121 16,170 57,800 2006/07 -2,218 -5,565 20,787 2007/08 -2,218 -5,565 20,787
There will be additional disturbance payments funded from revenue budgets to cover removal costs and disconnection charges, estimated at approximately £250 per tenant. Budgets have been identified within Housing Assessment Service to finance the £2,121 General Fund cost resulting from the closure.
The costs to the Housing Revenue Account (HRA) £ 16,170 in 2005/06 will be met from the HRA budget. This will be replenished by the savings in 2006/07 and future years. Savings will arise from reduced running costs including repairs and by an increase in Housing Subsidy due to these properties being decanted.
The Capital Costs represents the Home loss payments of £3,400 per tenancy as per the Land Compensation Act 1973 section 29-33. These costs will be met from within the Home Loss compensation line in the approved Housing Capital Programme for 2005/06.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
The closure of Heather Court Sheltered Housing Scheme, Tetlow Street (HSG/24)Report | 4 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.