Resolved
Resolved that the recommendation as amended be approved.
Planning Committee 2010/21 old approved this item on Tuesday 6 December 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation as amended be approved.
Ward: Kirkdale Site: Liverpool Waterfront (between Alexandra Dock and Sandon Half-Tide Dock), Liverpool, L3
Proposal: To extend the adjacent Wind Farm by the erection of 5 no. wind turbines
Applicant: Mersey Docks & Harbour Company
Application No: 05F/2712 Date Valid: 22nd August 2005
D. C. Team: City North
Recommendation Approve with Conditions _______________________________________________________________
Case Officer Report
Site Description
The application site comprises the port wall running from the north western tip of Alexandra Dock in Sefton to the south western tip of Sandon Half Tide Dock in Liverpool. The site is located on the western extent of the Port of Liverpool, on the seaward edge of the dock estate. The site is approximately 2.5 miles long and straddles the boundary between the local authority areas of Liverpool City Council to the south and Sefton Council to the north. The site is characterised by industrial and port related uses. To the north of the site lies Seaforth Dock and Container Terminal, this is the existing location of 6 wind turbines.
The Proposal
The application proposes to extend the existing wind farm at Seaforth by 5 turbines. Planning applications have been submitted to both Sefton and Liverpool. It is proposed to site 3 of the turbines in Sefton and 2 in Liverpool.
The turbines would have an overall height of 135m. In comparison, the wind turbines at Seaforth are 75m in height. Each of the proposed turbines comprise of; i) a concrete base approximately 20m x 20m; ii) a three part modular tower 80m high (4.15m diameter base, 2.3m diameter at the top); iii) a hub, 2m high;
Planning Committee 6 December 2005 iv) a nacelle (body of the turbine housing gears and cooling systems) 10m high, and; v) 3 rotor blades each 44m in length, giving an overall rotor diameter of approximately 90m.
Each of the turbines would contain a mechanism which would allow it to move and turn itself towards the wind. In this area the prevailing wind is from the west / south west and as such they would face that direction for a large part of the time. The turbines would stop automatically in high winds. The turbines would be linked to the main electrical distribution network and have an output of 3MW giving a total combined capacity of 15MW.
The location of the turbines has been selected to retain a separation distance of 300-450m. • Turbines 1, 2 and 3 would be located within Sefton, turbine 1 would be the most northerly of the 5 proposed. • Turbine 4 would be located between scrap metal operations and Merlin, dry bulk specialists, who operate from West Huskisson Shed. The turbine would be sited opposite the lock between Canada Dock and Huskisson Dock. • Turbine 5 would be the southern most turbine. It would be adjacent to a storage facility operated by North West Trading, opposite the dock gate between Huskisson Dock and Sandon Half Tide Dock.
Turbine 4 would be sited away from the World Heritage Site and Buffer Zone. Turbine 5 would be on the outer boundary of the Buffer Zone.
The planning application is accompanied by an Environmental Impact Assessment comprising; • Environmental Statement • Non-Technical Summary to Environmental Statement • Planning Statement • Landscape and Visual Assessment • Appendices.
Relevant Site History
An application for 6 wind turbines at Seaforth was submitted to Sefton 1995. Following a pubic enquiry the development was allowed at appeal.
Response to Consultations
Site notices were posted in the vicinity of the application site.
Planning Committee 6 December 2005 • City Councillors – Objection from Councillor Malcolm Kennedy on the grounds of impact from noise on the residents of the flower streets.
• Area Committee – At its meeting 05/10/05 the Committee expressed support for the application.
• Other Consultees
English Heritage – No comments.
Liverpool John Lennon Airport – No objection.
Wirral MBC – object to the proposed development for the following reasons:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Liverpool Waterfront (between Alexandra Dock and Sandon Half-Tide Dock), Liverpool, L3 (Kirkdale Ward)Report | 10 pages | DownloadRead as text |
PDF |
alexandra sandon half dockReport | 1 pages | Download |
Follow Planning Committee 2010/21 old at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 2 June 2020 be approved. | Approved | Open |
| 2 Jun 2020 | Minutes of the Last MeetingResolved that the minutes of the Virtual Meeting of 26 May 2020 be approved. | Approved | Open |
| 26 May 2020 | Minutes of the Last Virtual MeetingsResolved that the minutes of the Virtual Meetings of 5 and 12 May 2020 be approved. | Approved | Open |
| 31 Mar 2020 | Minutes of the Last MeetingAgreed that the minutes of the last meeting held on 10 March 2020 be approved. | Agreed | Open |
| 10 Mar 2020 | Minutes of the Last Meeting 18 February 2020Resolved that the minutes of the last meeting held on 18 February 2020 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.