Resolved that in relation to the City Centre Environmental Improvement Plan (EIP) Performance Plan 2005/6 - (i) the progress of the projects contained within the report, and expenditure of £1,955,403 from the capital programme and £118,256 of revenue expenditure took place during 2004/5, be noted. All expenditure has been externally funded; (ii) the proposed Environmental Improvement Performance Plan for 2005/6, be approved; (iii) the Executive Director (Regeneration) be authorised to sign off the Environmental Improvement Programme Performance Plan for 2005/6; (iv) in principle approval be given to the schemes planned for the Environmental Improvement Programme for 2005/6 as detailed in the Performance Plan, subject to f urther reports on a project by project basis to request final approval; (v) the City Council’s capital programme be amended to reflect the 100% externally funded anticipated spend of £1,785,670 in the financial year 2005/6.; (vi) the City Council’s revenue programme be amended to reflect the 100% externally funded anticipated £124,000 spend in the 2005/6 financial year; and (vii) authority be granted for the Executive Director (Regeneration) in consultation with the Executive Member (Regeneration), to vire money between projects within the EIP Performance Plan of a value below £250,000, in order to maximise expenditure this financial year, should there be a delay in spend on any of the projects.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
i. Update Members on the progress of the City Centre Environmental Improvement Programme (EIP) 2003/4 to 2005/6.
ii. To advise Members of and seek approval for the City Centre EIP for 2005/6 (as attached in Appendix 1).
iii. To seek members approval for the Executive Director for Regeneration to be granted permission to sign off and submit the City Centre EIP Performance Plan for 2005/6.
iv. To advise members of, and seek preliminary approval for the schemes within the City Centre EIP Performance Plan for 2005/6 (Appendix 1):
Background
2.1A report (EDR/407/02) was submitted to Members in November 2002 that focused on the Land Reclamation Programme for Liverpool and the City Centre. The report included the delivery, maintenance and management arrangements to be taken forward as part of the city’s Land Reclamation Programme for 2002 – 2005.
2.2Following this report, the City Centre EIP was established (with equal funding from both NWDA and EP). A Performance Plan was produced for 2003/4 following consultation with the North West Development Agency (NWDA), English Partnerships (EP), and Liverpool Vision. The grant funding for the City Centre EIP requires a Performance Plan to be agreed by all parties before the beginning of each financial year. The Performance Plan establishes a baseline of projects to be delivered within the financial year. The 2005/6 Performance Plan has been delayed due to late notifications from the NWDA with regards to the levels of funding available.
2.3Originally, secured funding for the 3 year Programme (2003/4-2005/6) was as follows:-
Revenue Preliminary Works (NWDA) £123,000 Programme Management (NWDA) £227,070
Capital City Centre EIP (EP) £4,500,000 City Centre EIP (NWDA) £4,450,500 Capital Modernisation Fund (ODPM) £ 350,000 Arts Council England £ 4,995 Private Sector £ 122,200 Total (Capital + Revenue) £9,777,765
2.4Also it should be noted that, the funding provided by the EP & NWDA during 2005/6 has been limited due to their own financial constraints, reducing the originally anticipated City Centre EIP programme for 2005/6. There is a possibility that additional funds may become available during 2005/6 from either the NWDA or EP. For this reason, slippage and pipeline project have been identified. Projects identified as slippage project will be delivered during 2005/6 if funding is made available (Slippage projects are those that have the potential to be delivered within 2005/6, should funding become available). Pipeline Projects (schemes that have been identified for future delivery) could also be delivered within 2005/6 if funding is made available, however, slippage projects will take priority. It is also to be noted that some of the Capital resource originally allocated to the City Centre EIP will now be redirected by NWDA to other key projects such as the Cruise Liner Terminal. The impact of this has meant that the overall City Centre EIP has been reduced.
3. Project Update
3.1The previous year of the Programme (2004/5), saw many achievements which are detailed below: i. Procedures
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.