Accommodation and Support Contract between LCC and Home Office National Asylum Support Service (NASS) (SC&CS/3)

Approved Executive 1 paper

Executive Board approved this item on Thursday 13 April 2006. Below is the council's own wording, with the papers it was decided on.

Item194e

Resolved

Resolved that – (i) upon finalisation of contract details specific to Liverpool, the City Solicitor be authorised to sign the contract for a period of five years; (ii) upon reaching preferred service user volume approval be granted for up to two additional scale 3 floating support staff to be recruited, provided the cost of these can be fully covered by the contract. Any additional recruitment will be offered on a fixed-term contract basis only; (iii) it be noted that the contract is forecast to be self financing based on the minimum volume of service users awarded by National Asylum Support Service (NASS) and is costed to the specific direct delivery team in the required format laid out in the Best & Final Offer proposa (BAFO) submission to the Home Office; (iv) it be noted that NASS cannot guarantee that they will request the council to support the minimum volume of service users and in the event of the number becoming uneconomical to support then the Council will enter into negotiations with NASS to increase the prices and make the service self financing; (v) should numbers become uneconomical to support and negotiations with NASS are unsuccessful, officers will recommend action to the Executive Board to ensure the service becomes self financing; (vi) it be noted in reference to paragraphs (iv) and (v) above that although NASS does not guarantee minimum or preferred service user numbers that three hundred and eighty service users are already awarded to the Council contract to be transferred over to support in the transition period following contract signature. This figure takes the supported service users to the threshold of maximum volume; (vii) it be agreed the operation of the Asylum Team remains the first contact point for the specific service user group that will be referred under the dispersal arrangements to be provided with a dedicated directly accessible key-worker support; and (viii) it be recognised that the NASS statement of requirements and commitment to delivery of contracted services by Liverpool City Council maintains, through the Asylum Team, an operational site that provides an exclusive contact and front counter reception service to asylum seekers that are placed under these provisions and in recognition of their vulnerable position, language and need for high confidentiality.
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 10 pages

Executive summary

This report seeks approval for the City Council to sign a new contract with the Home Office through the National Asylum Support Service (NASS) to provide for direct provision of accommodation and support to Asylum Seekers in the City under national dispersal arrangements. This follows on from the existing NASS contract operated by the City Council Asylum Team that expires February 2006 with an extension to April 2006. The new contract is for a 5 year period.

The Executive Board gave approval to enter into negotiations following the report and recommendations of the Asylum Seekers & Refugee Scrutiny Panel through the Housing & Community Safety Select Committee to engage constructively with NASS and to ensure that Liverpool has a greater influence and control of dispersal arrangements affecting the city which hosts one of only two Asylum Screening Units (ASU) in the Country. The Executive Board recommendations also included that the Asylum Team increased the percentage of direct contract support to dispersed Asylum Seekers within the set cluster size for the region. This was to serve two purposes, ensure that a larger number of those dispersed to Liverpool are ensured the high quality of service that has been provided by the city council and to ensure adequate income to maintain the Asylum Team in its existing role.

Negotiations around new contracting arrangements with NASS were lead by the Service Manager for Refugees and Asylum Seekers with input from Regeneration Finance and Legal Services. The negotiation process required the submission of a detailed Invitation To Negotiate document (ITN) and concluded in November 2005 with the submission of a Best & Final Offer proposal (BAFO) that went to the Home Office Business Scrutiny Committee for approval and Liverpool was formally awarded a contract on February 9th 2006 in accordance with the BAFO submission and the detailed proposals template.

The current NASS contract is property based, i.e. we are funded for the wrap around service and property costs on the basis of a two bed or three bed property. The new arrangements developed by the NASS 2005 Accommodation Strategy Team have been drawn up in accordance with Best Value and service user based proposals. On this basis LCC would charge NASS a set rate for each service user or family member in any property rather than a set property size rate.

The National average for family size groupings under asylum dispersal is 3.5 on this basis the financial template Liverpool provided within the BAFO submission set a price for each service user that would guarantee all service and operational costs at a minimum volume of 175 service users from a preferred volume of 375 and to a maximum of 400. The current contract already has around 175 service users in properties and provides the break even point. The awarded contract meets our preferred volume and would cover forecast operational costs and potentially generate additional income to the city council. It should be noted however that NASS cannot provide guarantees on the number of asylum seekers they will request the Council to support. In the event that it becomes uneconomical to support at the agreed price the contract allows the council to enter into negotiations with NASS to increase the price or enter into termination procedure. To achieve this, the service will maintain a regular monthly financial monitor to ensure that the minimum service user levels are monitored and maintained This will be key to providing for all operational costs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Accommodation and Support Contract between LCC and Home Office National Asylum Support Service (NASS) (SC&CS/3)Report 10 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Liverpool

Search all
  1. Accommodation and Support Contract between LCC and Home Office National Asylum Support Service (NASS) (SC&CS/3)This decision
  2. Accommodation Based Housing Support Services for People Who Statutorily Homeless (HCS/9)Approved
  3. Family Accommodation Contract with National Asylum Support Service (NASS)Approved
  4. Replacement of Foley Close Mental Health Hostel by a New Person Supported Accommodation SchemeApproved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies