Resolved
Resolved that the recommendation be approved.
Executive Board approved this item on Friday 9 January 2004. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved.
The City Council has a small Asylum Support Team that is funded by the National Asylum Support Service (NASS) to accommodate and support single people and families who are asylum seekers classed as ‘interim cases’, that is people who applied for asylum prior to April 2000. The number of ‘interim cases’ is diminishing as decisions on their applications are made. As at 1 January 2003, the team was supporting 61 families and 100 single people. By December 2003, this had reduced to 48 families and 62 single people. The Home Secretary recently announced that the majority of remaining families within this group will be given leave to remain within the country. Single people will remain under interim arrangements until their cases are decided by the Home Office and Courts.
The costs of supporting the interim cases are recovered from Home Office grant funding based on a fixed unit rate per single or family. The reduction in numbers in 2003/04 is expected to fall below the minimum number required to break even. Section 99 of the Immigration and Asylum Act 1999 allows a local authority to provide support for asylum seekers and their dependants in accordance with arrangements made by the Secretary of State.
This report seeks approval for the Council to enter into a new contract with NASS for the provision of accommodation and support for an additional 60 asylum seeking families, under the NASS dispersal arrangements. Under the terms of the contract Family referrals will be only those deemed eligible for support by the National Asylum Support Service, who have recorded claim for asylum in the UK. The overall number of asylum seekers within the city will remain within the Home Office’s recommended guidelines. The contract will be for a period of two years. Accommodation will be procured from Registered Social Landlords and private landlords. Support for asylum seekers will be provided by the Council’s Asylum Support Team. The contract will, for the first time, provide the Local Authority with an input into the dispersal process which has previously been carried out solely between NASS and the private sector.
Most asylum seekers dispersed by NASS to Liverpool are currently placed directly with private housing providers. There are around 2,000 people living in the city under these arrangements. The current contracts will expire in March 2005. New arrangements for the dispersal of asylum seekers will be implemented after this date. The shape of these arrangements is still being considered and consulted upon by NASS, but the strategic aim is to engage with Local Authorities in a partnership arrangement. The City Council’s Asylum Support Team and its line management within Housing Assessment Services has responsibility for co-ordinating corporate and multi-agency support for all asylum seekers and refugees within Liverpool. The funding for these responsibilities is derived from the NASS Enabling Grant of £40,000 per year and the income for the provision of support for the ‘Interim Cases’. The grant to Liverpool is to support the development of relationships and support for asylum seekers across Merseyside, Cheshire and Cumbria. Other local authorities within the sub-region have expressed interest in entering into similar accommodation contracts if Liverpool successfully concludes this contract with NASS.
Executive Member/Director recommendation (Cllr Flo Clucas /Tony Hunter)
That –
(i) upon the conclusion of negotiations, the City Solicitor be authorised to sign the contract for a contract period of two years;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Family Accommodation Contract with National Asylum Support Service (NASS)Report | 5 pages | DownloadRead as text |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.