Resolved that in relation to - (i) Granby : · the City Council commits £51,054.53 from the First Phase of the City’s Children’s centre capital allocation for 2004-06, for the additional costs; and · approval be given to increase the authorised expenditure on the contract to £1,404,181; (ii) Walton: · the City Council commits £45,281.00 from the First Phase of the City’s Children’s centre capital allocation for 2004 -06, for the additional costs; and · approval is given to increase the authorised expenditure on the contract to £624,987; (iii) Fazakerley : · the city council commit £60,695.00 from the First Phase of the City’s Children’s centre capital allocation to cover the difference in the estimated cost and the tender cost for the construction of Fazakerley Children’s Centre at Barlow’s School; bringing the total Sure Start children’s centre capital allocation for this scheme to £1,640,932. This, together with £100,000 from the Early Years revenue budget will finance £1,414,441.00 of construction work, £183,877.00 20:20 Liverpool fees and residual charges, £12,614 disbursements, including Liverpool School Services contractual charges of £100,000 and £30,000 for furniture and equipment; and · the lowest tender in the sum of £1,414,441.00 for the construction of Fazakerley Children Centre be accepted and the City Council enter into a contract with Thomas Barnes; and (iv) the capital programme be amended accordingly. CHS/57
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is 1) To seek authority to commit £157,030.53 from the First Phase of the City’s Sure Start Children’s Centre Capital allocation for 2004 – 2006 to cover the increased costs of three First Phase Children Centre capital programmes: Granby, Walton and Fazakerley. 2) To seek authority to amend the capital programme accordingly.
Project variances
Reasons for these variances in the three Children Centre Capital Programmes are identified below:
1. Granby Children Centre – BEERG25
Approval is sought to commit an additional £51,054.53 from the City’s Sure Start Children centre capital allocation for 2004-2006 to cover unforeseen additional costs relating to the construction of Granby Children Centre.
The additional costs relate to a number of elements of work which could not have been envisaged at tender stage and lie outside the parameters for work that would normally be covered by the contingency sum. The items relate to statutory services - main electric, main gas and main water and mains service-general; as well as asbestos.
The Sure Start Unit approved the additional costs on the 31st March 2006 and confirmed that the costs can be met from the First Phase of the City’s Sure Start Children’s Centre Capital allocation for 2004 -2006.
2. Walton Children’s Centre – BEERG11
Approval is sought to commit an additional £45,281.00 from the City’s Sure Start Children Centre capital allocation for 2004-2006 to cover unforeseen additional costs relating to the construction of Walton Children’s Centre.
The additional costs relate to four factors 1) Investigation works to expose the ground drainage system which was found not to be in the locations indicated on the existing drawings. 2) Additional steelwork: It was assumed that due that to the existing buildings age there would be existing steel beams however this was not he case. 3) Breaking out obstructions to the ground and increased depth of piling required. 4) Delays and subsequent extension of time for Category 3 Asbestos Survey by Scope. The Sure Start Unit approved the additional costs on the 29th March 2006 and confirmed that the costs can be met from the First Phase of the City’s Sure Start Children’s Centre Capital allocation for 2004 -2006.
3. Fazakerley Children’s Centre – BEERX21
Approval is sought to commit an additional £60,695.00 from the City’s Sure Start Children Centre capital allocation for 2004-2006 to cover the difference in the estimated cost and the tender cost.
Prior to the project going to tender approval was given by the Sure Start Unit to the estimated cost of the scheme in the sum of £1,580,237. (This figure is inclusive of professional fees, statutory fees and loose furniture and equipment.)
On 3rd March 2006 the Executive Board approved the commitment of £1,580,237 from the City’s Sure Start Children Centre capital allocation for 2004-2006, for the construction of Fazakerley Children’s Centre. In order to enable construction to commence prior to the end of March 2006 the Executive Board also approved the acceptance of the lowest tender and agreed for the City Council to enter into a contract with the successful tenderer providing the lowest priced tender was within the approved construction budget of £1,360,698.
The lowest competitive tender received was for £1,444,441; approximately £84,400 higher than the estimated cost. Cost reductions of £30,000 were identified and the Sure Start Capital Strategy Team approved the cost of the scheme at £1,640,932.00. (This figure is inclusive of professional fees, statutory fees and loose furniture and equipment.)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.