Resolved
Resolved that the recommendation be approved subject to the Executive Member (Special Initiatives) replacing the Executive Member (Regeneration and Transport) on the BSF Project Board. EDE/2
Executive Board approved this item on Friday 28 April 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the recommendation be approved subject to the Executive Member (Special Initiatives) replacing the Executive Member (Regeneration and Transport) on the BSF Project Board. EDE/2
1. Building Schools for the Future (BSF) is a major national programme to transform secondary education. The programme will be delivered through a series of ‘Waves’. Liverpool is in Wave 2 and Wave 4.
The DfES has established a ‘Partnership for Schools’ (PfS) which will oversee the national programme.
The Authority is required to complete a number of steps in order to be able to procure the programme. The first step was the production of an Education Vision.
This work was completed during May 2005. The Education Vision is the major component of the Strategic Business Case which is the second step. Both of these documents were presented to Select Committee and the Executive Board and the Strategic Business Case was approved by the Board.
The DfES has formally written to the Authority accepting both the Vision and the Strategic Business Case.
2. Outline Business Case (OBC)
The Strategic Business Case included the phasing of all schools into BSF across Waves 2-4. This was based on a priorities exercise, availability of sites and the nature of the building work required, new build, remodelling or minor refurbishment which informed the costing. The envelope of funding identified for Wave 2 was £140 million.
In order to produce the Outline Business Case the following issues need to be addressed:
A .Site availability A. School organisation issues B. Affordability C. Procurement methodology to be pursued D. Governors agreement In addition the Authority has to undertake a Gateway Review through the 4Ps. This was done in the week beginning 5 September and in most areas the Gateway team were satisfied that the work had been completed. The outstanding areas identified were known to the team and have been dealt with. They are discussed later in this report. The present OBC deals with all Wave 2 schools.
• West Derby • Ernest Cookson • Alsop • King David High School • Croxteth Comprehensive with the option of including Meadow Bank in the building • Cardinal Heenan • Broughton Hall • Gateacre • Hope • New Heys
In the case of the majority of schools there are no site issues or school organisation issues. Site issues for Gateacre are in the process of being resolved and consultation with stakeholders is continuing. Meetings have been held with all of the Governors. The initial governors agreement is in preparation and will be included in the OBC.
3. Major Issues
Affordability
There are two main issues in relation to the affordability of the scheme.
• The over all capital available • Life cycle capital for schools
PfS calculate the capital available for the Wave 2 schools on the square metres required based on pupil numbers. They provide 50% of the total square meterage at new build rate, 35% at re-modelling rate and 15% at minimum refurbishment rate. It is therefore unrelated to the actual costs of the proposed schemes in Wave 2.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Building Schools for the Future: Outline Business Case (CHS/58)Report | 5 pages | DownloadRead as text |
PDF |
CHS.058 BSF outline bus case docReport | 193 pages | Download |
Follow Executive Board at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Apr 2010 | Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. | Approved | Open |
| 23 Apr 2010 | New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... | Decided | Open |
| 23 Apr 2010 | 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... | Decided | Open |
| 23 Apr 2010 | Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... | Approved | Open |
| 23 Apr 2010 | Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.