Resolved that – (i) a budget of £375,000 be established from the balance of the Planned Maintenance Fund 2006/07 inclusive of 20:20 Liverpool fees to fund the cost of urgent repairs to Anfield Infants and Junior Schools; (ii) a budget and £600,000 be established from the balance of the Modernisation Fund (primary need) 2006/07 inclusive of 20:20 Liverpool fees to fund the cost of urgent repairs to Pinehurst Primary School; and (iii) the Capital Programme be amended accordingly. CHS/10
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to seek approval to set aside a budget to carry out urgent repairs to Pinehurst Primary and Anfield Infants and Junior Schools
Background In 2005 the City Council submitted a bid for Targeted Capital Funding to the DfES to rebuild Pinehurst Primary and Anfield Infants and Juniors. The bid recognised that the three schools are amongst the poorest in the City in terms of their condition and suitability, that funding major capital works through the annual formulaic capital allocations the City receives for schools would not be feasible and that the costs associated with complete refurbishment of all schools on their present sites (for which a number of feasibility studies have already been carried out) is prohibitive.
All three schools are old with the Pinehurst buildings dating from the 1920’s and 1940’s and Anfield Infants and Juniors dating from the latter part of the 19th century. Total maintenance backlog has been assessed as close to £2m but this doesn’t reflect the significant costs of improving the suitability (fitness for purpose) of the three schools nor adaptations that are required to improve accessibility and provide modern facilities.
The bid was, however, unsuccessful.
For Pinehurst Primary, compounding the problems of the general condition of the school, is the fact that it currently operates from a split site which adds complications around the management and operation of the school and puts strain on already overstretched budgets.
Opportunities to bid for Targeted Capital Funding are limited to one bid every two years – 2007 for the City Council - and whilst the schools remain a priority for replacement the reality is that this is unlikely to be achieved before the next major strand of Government investment is in place, namely the Primary Capital Programme from which funding is to be made available to all local authorities from 2009/10.
In the interim therefore it is necessary to ensure that some of the more significant repairs that have a direct or indirect impact on health and safety on pupils and staff are attended to given that the time frame for new schools being available is a minimum of 5 years away. The following areas of necessary repair and refurbishment have been identified for the three schools: Anfield Infants and Juniors
• Replacement and overhaul of windows • Repairs to flat and pitched roofs and rainwater goods • Eradication of dry rot • Chimney stack repairs • External pointing • Plaster repairs and painting • Works to improve accessibility
Pinehurst
• Repairs to the roof covering, lead flashing and rainwater goods including parapets • Structural repairs to the external fabric of the building including corroded window lintels • Repairs to existing single glazed windows, including replacement where required. • Repairs to ceilings, walls and floors where required • Re-plaster walls damaged by water ingress • eradicate areas of dry rot. • Repair and refurbish boys and girls toilet blocks • Improvements to security arrangements to the main entrance including improvements to access • Re-surface playground • Replacement fire escape • Redecorate internally after repairs • Works to heating systems • Nursery play area • Works to improve accessibility
In addition to the above electrical re-wires are proposed for both schools. The costs of these are still being determined and will be brought forward in a separate report relating to proposed electrical works to community schools for 2006/07.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.