Resolved that – (i) the lowest tender in the sum of £572,228 for the construction of a new kitchen and hall extension at Booker Avenue Infants School be accepted and the City Council enter into a contract with Gawne and Roberts Construction Ltd.; (ii) the City Council incur professional fees of £80,214 from 20:20 Liverpool, plus residual costs of £9,626 and disbursements of £24,000 including costs associated with the removal of asbestos; (iii) the budget for the project be increased by £186,068 to reflect actual costs compared to original budget estimates to be funded from the balance of Modernisation Funding 2006/07; and (iv) the Capital Programme be amended accordingly. RT/12
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
The purpose of the report is to seek approval to accept a tender for the construction of a new school kitchen and extension onto the hall at Booker Avenue Infants School.
Background
On 17 March 2006 the Executive Board approved the establishment of a budget of £500,000 within the Children’s Services Capital Programme for a proposal to develop a new kitchen and dining facility at Booker Avenue Infants and Junior Schools. At the moment the schools use a shared kitchen that is housed in a 1930’s detached concrete building located between the junior school and the infants’ main entrance. The building contains a dining room for the junior school which is also used for breakfast clubs and after school activities. Meals for infants children are cooked in the kitchen and taken to a separate servery in the school adjacent to the infants’ hall which they use for dining. The building is in very poor condition and has reached the end of its useful life.
In consultation with both schools, governors and 20:20 Liverpool a number of options for a replacement building were explored in detail. These included providing a detached facility in the same location or on a different part of the school site or extending onto one of the schools. Ultimately the best solution is considered to be extending onto the infants’ hall. The proposal will provide a multi-purpose room partitioned off from the main hall with a separate entrance from the outside providing a space for the junior dining at lunch times, breakfast clubs, after school activities plus additional learning space for the infants’ school during the day. A new kitchen will be constructed at the end of the infants’ hall with separate serveries into the existing hall and new multi-purpose extension to cater for both infant’s and junior lunches. Planning permission for the project was granted on 9 March
In accordance with Standing Orders tenders for the proposed works were invited from 5 firms and returned to the City Council on 10th May 2006. The lowest priced tender received was from Gawne and Roberts Ltd in the sum of £572,228. 20:20 Liverpool have checked the priced schedule submitted by the lowest tenderer and have confirmed that there are no arithmetical errors and that the price submitted is competitive and represents value for money. Interim Executive Director recommendation: Stuart Smith recommends that –
(i) the lowest tender in the sum of £572,228 for the construction of a new kitchen and hall extension at Booker Avenue Infants School be accepted and the City Council enter into a contract with Gawne and Roberts Construction Ltd.;
(ii) the City Council incur professional fees of £80,214 from 20:20 Liverpool, plus residual costs of £9,626 and disbursements of £24,000 including costs associated with the removal of asbestos;
(iii) the budget for the project be increased by £186,068 to reflect actual costs compared to original budget estimates to be funded from the balance of Modernisation Funding 2006/07; and
(iv) the Capital Programme be amended accordingly
Key Decision: Yes
Forward Plan: Yes
Implementation effective from: 4 August 2006
Timescale for action:
The project is programmed to start at the beginning of the school summer holidays with a contract length of 26 weeks
Reason(s) for Recommendation:
The works outlined in the report relate to priorities of the Children’s Services capital programme reflecting strategic as well as asset management issues.
Alternative options considered
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.