Resolved that – (i) the commitment to the revised and possible costs of the Central Library and Archive PFI Redevelopment scheme as detailed under the Financial Implications of the report submitted be confirmed and that it be noted that the annual contribution may vary, but that further reports and updates of the expected affordability gap will be submitted following receipt of tenders and prior to appointment of a Preferred Bidder; (ii) the Head of Libraries and Information Services be authorised to submit the OBC Supplement (Appendix 1) submitted to the DCMS to secure endorsement of the project by the PFI Project Review Group; and (iii) the establishment of the PFI Project Board and its revised terms of reference be approved as set out in the “Terms of Reference of the PFI Project Board” (Appendix 2) submitted to achieve successful procurement and delivery of the scheme. RES/7
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Read, Enquire, Discover, Learn Liverpool Central Library and Archive PFI OBC Supplement
INTRODUCTION
Liverpool City Council’s Outline Business Case for the redevelopment of Liverpool Central Library and Archive through a Design Build Finance and Operate contract under the Private Finance Initiative was submitted to the Project Review Group for consideration at its meeting of 18 April 2006.
However at the meeting PRG expressed some concerns and asked that further work be carried out prior to their endorsement of the scheme. The further work required by PRG is set out in the questions of the meeting (extract from PRG Minutes Appendix 1) consisting of 11 items. Responses to these eleven questions are included in this OBC supplement, grouped within 4 sections plus appendices. Where appropriate, reference is made to the relevant section of the full OBC.
Approval to submit the OBC Supplement was given by the Executive Board of Liverpool City Council at its meeting on 28 July 2006. An extract of key sections from the report to the Executive Board, and Board questions form Appendices 2 and 3.
SECTION 1 AFFORDABILITY AND CITY COUNCIL COMMITMENT (PRG question nos. 1, 7, 2, 6, 11)
1.1Impact of delays on affordability
PRG question no. 1: The impact on affordability that any potential delays (up to 12 months) in the project should be considered and analysed.
The full affordability analysis was contained in section 7.4 of the OBC.
A review of the financial effect of a 12 month delay in the programme for the project has now been carried out by the City Council’s financial advisors, taking into account the outcome of the review of costs undertaken by Cyril Sweett, independent construction consultants (Appendix 4).
This has been done in two stages
1. Revised timetable / costs
The model has been amended based on the new programme (Appendix 6) which assumes financial close in March 2008, and on the revised capital costs from Cyril Sweet based on this revised programme.
The revised construction costs show an increase of £1.2m compared to the previous estimate mainly due to inflation. This increase in construction costs has a knock on effect on other costs such as bank fees and interest during construction, so that the total increase in funding is £1.5m.
Based on this increase in construction prices, it is estimated that, at 2010/2011 prices, the Unitary Charge (UC) would need to increase to approximately £6.447m.
Read, Enquire, Discover, Learn Liverpool Central Library and Archive PFI OBC Supplement
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.