CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Liverpool City Council
Executive Board, Friday 8 September 2006

Norris Green Wardens (NH/19)

Approved Executive 1 paper

Executive Board approved this item on Friday 8 September 2006. Below is the council's own wording, with the papers it was decided on.

Item66c

Resolved

Resolved that – (i) the development of the IES Business Plan be approved; and (ii) the Warden Service be undertaken by IES at a date to be agreed by the Interim Executive Director (Regeneration) in consultation with the Executive Member for Neighbourhoods and Housing. EH/6
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 4 pages

Executive summary

Over the past financial year the Council has been engaged in a city-wide review of environmental warden schemes which culminated in a feasibility study to determine, amongst other things, the potential for a social enterprise to be established as a positive ‘exit strategy’ to enable any successful NRF funded schemes to continue post Year 5 NRF.

The background to the review was an appreciation that sufficient NRF would not be available in Year 6 to allow the plethora of current schemes to continue after March 2006.

The work was carried out via a sub-group of Strategic Housing Partnership. ELECT were commissioned, via Liverpool Plus, to carry out the feasibility study. They concluded the schemes in existence had great support; there was demand for schemes in other areas; and, there was potential for a Social Enterprise to be set up with a view to growing the provision across the City.

In December 2005 SHP agreed the recommendation in principle and also agreed Plus Group would take the lead in developing the Social Enterprise.

Meanwhile, UK Programmes Team earmarked £300K in the Year 6 NRF programme to aid development of the new organisation and assist in the transitional arrangements. Plus Group has acknowledged the City Council’s immediate priority is to keep a warden service on the Boot estate whilst regeneration is taking place. This is an important redevelopment area in the City; but there is no mainstream funding to pay for a warden service post March 2006. Plus Group on behalf of SHP has therefore confirmed that seven Boot Wardens will be paid from this NRF allocation and other funding streams whilst arrangements are made to change/shift the current service arrangements.

Plus Group/ In Environmental Services, the developing Social Enterprise, are currently firming up their Business Plan in consultation with Neighbourhood Managers; Enterprise-Liverpool; Employment Programmes Team; Chief Executives of the RSLs, and Job Centre Plus. The change in provider to IES will have transfer implications for the 7 no. staff. Discussions have been on-going with the Wardens who have, generally speaking, been content that a sustainable solution that will enable continuation of their employment has been found. These operatives now need to have formal HR advice on TUPE issues and be afforded the opportunity to be introduced to IES, the developing Social Enterprise, pending their transfer to this organization once their Business Plan has been finalised.

Executive Member for Neighbourhoods and Housing Councillor Marilyn Fielding/ Interim Executive Director for Regeneration, Ben Dolan - recommendation:

The Executive Board approve i) the development of the IES Business Plan subject to its adoption ii) the Warden Service be undertaken by IES at a date to be agreed by the Interim Executive Director in consultation with the Executive Member for Neighbourhoods and Housing

Key Decision:

No

Forward Plan/5 days notice/special urgency:

No

Implementation effective from:

15 September 2006.

Timescale for action:

This will depend on on-going discussions with the Wardens, Trades Unions, Human Resources, IES and Plus Group. However, in the best interests of the Wardens for whom there is no mainstream funding, this is being implemented as soon as possible and prior to the end of this financial year.

Reason(s) for Recommendation:

To enable the environments Warden Service provision on the Boot estate whilst redevelopment is on-going. Alternative options considered:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Norris Green Wardens (NH/19)Report 4 pages DownloadRead as text

At this meeting

Whole meeting
65Minutes of the Last MeetingApproved 66aYouth Opportunity Fund and Youth Capital Fund (L/4)Decided 66bAlderwood Resource Centre, Bridge Chapel Heath Road (RES/15)Decided
66cNorris Green Wardens (NH/19)This decision
66dSmoke Free Liverpool (EH/6)Noted 66eLocal Nature Reserve, Allerton (EH/10)Decided 66fCommuted Sum Funded Environmental Improvements 2006-07 (EH/11)Approved 66gThe Wellington Rooms, Mount Pleasant: Action for Repair and Re-use (EH/12)Agreed 66hBelle Vale Children’s Centre (CHS/15)Approved 66iLime Street Gateway (R&T/17)Decided 66jWhitechapel Improvements (R&T/19)Agreed 66kObjective 1 - Liverpool Neighbourhood Regeneration Programme - Commissioning Exercise - Extension Projects (R&T/20)Decided 66lObjective 1 Liverpool Neighbourhood Regeneration Programme - Commissioning Exercise for Liverpool Atlantic (R&T/21)Decided 66mObjective 1 Neighbourhood Regeneration Programme - Commissioning Exercise for Alt Valley (R&T/22)Decided 66nObjective 1 Neighbourhood Regeneration Programme - Commissioning Exercise for Eastern Link (R&T/23)Decided 66oObjective 1 Neighbourhood Regeneration Programme - Commissioning Exercise for South Central (R&T/24)Decided 66pFormer St Michael's Parish Hall, Upper Pitt Street, Liverpool 1 (R&T/25)Agreed 66qResourcing the A580 Strategic Investment Area (R&T/26)Approved 66rMoving the Past Forward - Heritage Investment Framework (EH/9)Decided 66sNew Anfield - The Restoration of Stanley Park (SI/3)On the agenda 67Turner Playing Field - Three Parks Neighbourhood Committee - 16 August, 2006Agreed 69aDCLG Capital Funding 2006/07 and 2007/08. Proposed improvement works to Direct Access Centres (SC&CS/5)Approved 70Summer Pops 2007 - Leisure and Culture Select Committee - 31 July 2006On the agenda 71aVoluntary and Community Sector Funding 2005/06 (EDE/7)Approved 72Exclusion of Press and PublicDecided 73aFinancial Assistance to Businesses (EDE/8)Approved 73bCreative Grants Programme 2006-07 (EDE/9)Approved

Who was there

14 of 20 attended
WB
Councillor Warren BradleyChair, present
DA
Councillor Dave AntrobusMember, present
PC
Councillor Paul CleinMember, present
FC
Councillor Flo Clucas OBEMember, present
MF
Councillor Marilyn FieldingMember, present
RM
Councillor Richard MarbrowMember, present
PM
Councillor Peter MilleaMember, present
MS
Councillor Mike Storey CBEMember, present
BT
Councillor Berni TurnerMember, apologies
KT
Councillor Keith TurnerMember, present
CH
Colin HiltonOfficer, present
PH
Phil HalsallOfficer, apologies

All 20 on the meeting page

On this subject at Liverpool

Search all
  1. Norris Green Wardens (NH/19)This decision
  2. Former nursing home site, Long Lane, Walton, Liverpool L9 6DN (Norris Green Ward)Approved
  3. 183 Scargreen Avenue L11 3BA (Norris Green Ward)Approved
  4. Land at Deanscale Road, Rushmere Road & Bowscale Road, Liverpool 11 (Norris Green Ward)Approved
  5. Land at Branthwaite Crescent/Bowscale Road, Liverpool 11 (Norris Green Ward)Approved
  6. Inliverpool Special Purpose Vehicle - Norris Green Land Transfer (Phase 1b) (L/25)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies