Resolved that – (i) permission be given to proceed with the design and construction of the Lime Street Gateway project; (ii) authority be given to the Interim Executive Director (Regeneration) to accept a capital grant from NWDA of £975,000 and £600,000 from ERDF M21 funds to facilitate the financing of the scheme. The City Council will thereby accept the role of accountable body for the NWDA grant; (iii) the City Council’s 2006/07 capital programme be adjusted to reflect a revised expenditure profile for the scheme totalling £1,950,000 financed by – · 2006/07and 2007/08 NWDA funding £975,000; · 2006/07and 2007/08 ERDF M21 funding £600,000; and · 2006/07 General Capital Resources £375,000; (iv) the City Centre Projects Team Manager be appointed as the nominated officer for monitoring compliance with the terms and conditions of the NWDA grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (v) in order to facilitate the scheme, a sum of £375,000 of 2006/07 general capital resources be allocated from the CCMS Package 2 Works project specifically to the Lime Street Gateway project; and (vi) the existing Lime Street/Whitechapel scheme at a cost of £167k be removed from the Capital Programme 2006/07. R&T/19
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
One element of the CCMS programme was for the enhancement of the proposed tram routes in the city centre to match other improvements to public realm. The area in front of Lime Street Station was expected to be affected by both lines 1 and 2 of the tram network. In the absence of the tram in the near future and with the proposed extensive infrastructure changes to the public realm areas fronting the station, the opportunity now presents itself to reconfigure the highway to take account of the anticipated traffic volumes, including in particular public transport and pedestrian flows.
The Lime Street Gateway (LSG) Development includes a large area of public realm that will enhance the appearance of the area in front of the station and present a feeling of ‘arrival’. The construction of this enhanced area of public realm is only possible if the highway fronting the station is reconfigured first, providing working space behind hoardings to enable those works to be constructed. The LSG scheme also involves extensive piling works to form an extended basement to the proposed tower building and these will be carried out behind the same hoardings in advance of the public realm works.
The principal objective for this scheme is to create a safer and more welcoming environment for pedestrians using the station and to this end the scheme will be introducing additional pedestrian crossings on both Lime Street and Skelhorne Street. The highway space will actually be reduced in width overall and therefore pedestrian crossings will generally be shorter in length. High quality materials will be used for the kerbs and paving on the station side and on central reservations with the footways on the west side being replaced in concrete materials to match existing.
Two sets of existing high mast lighting will be affected by the works and these will be replaced with suitable lighting to match the environment in this location.
It is expected that the works will commence on site in October 2006 with completion anticipated in March 2007. The Contractor’s programme does not take account of any Christmas break during November/December other than the period from 25th December until 8th January. Any enforced extension to this holiday period will therefore mean a later completion date.
The overall funding cocktail for the scheme comprises City Council general capital (SCE Capital Pot Borrowing) resources, NWDA funding £975k and ERDF funding £600,000. The majority of the spend on this scheme will be in 2006/07 with some carry over into 2007/08.
Transport capital programme funding was approved by the Executive Board at its meeting on 2nd June 2006 and this scheme forms part of the City Centre North package 2 included within the report setting out the overall transportation capital programme for 2006/07. The CC North Package 2 funding will now be reduced by the £375,000 required for the Lime Street scheme. Detailed design works are being carried out to enable the project to start on site in October 2006. City Council general resources have been used for this element of the scheme to date.
The proposals meet the following objectives:- • To create an attractive pedestrian environment; • To improve pedestrian access between the city centre and the Railway Station; • To ensure better traffic management by rationalising traffic movements; • To ensure appropriate capacity as part of the Strategic Highway Network; and • To accommodate development proposals and public transport requirements.
Executive Member/Director recommendation: Cllr. Millea, Cllr Turner / Ben Dolan
That
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.