Resolved that – (i) the City Council acts as the accountable body for the Sure Start Children Centre Capital Grant for the development of the Children’s Centre at Our Lady of the Assumption; (ii) subject to the approval of the Sure Start Unit, the City Council issue a capital grant to the Trustees of the Catholic Archdiocese in the sum of £846,624 inclusive of fees and charges financed from £846,624 Sure Start Children’s Centre Capital; (iii) the City Council shall enter in to an appropriate legal agreement with the Trustees of the Catholic Archdiocese to protect the City Council’s interest with regards the development of the project, fulfilment of the conditions of the Sure Start capital grants including clawback arrangements in the event that Children’s Centre Services cease to be delivered from the site; (iv) approval be given to the re- siting of the LA Belle Vale Day Nursery and for the site to be declared surplus to operational requirements once vacant to be transferred to the Head of Property and Asset Management for disposal; and (v) the Capital Programme be amended accordingly. R&T/17
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
BELLE VALE WARD STATUS – PUBLIC CHS/15 Portfolios: Executive Members: Children Services / Resources Cllr Paul Clein / Cllr Keith Turner Date of submission: Subject: 17 / 23 August 2006 Belle Vale Children’s Centre Report No: CHS/55/06 Contact officers: Background Papers: CHS/06/06 Suzanne Metcalfe– 225 6251 Rob Gilland – 225 6270
Executive summary: The purpose of this report is to seek authority to allocate £846,624.00 from the City’s Sure Start Children’s Centre Capital as a grant to the Trustees of the Catholic Archdiocese to finance the new Bellevale Children’s Centre co- located at Our Lady of the Assumption Catholic Primary School. The capital scheme will also include the relocation of the Infant School onto the Junior School site, to produce a single site school. The scheme will involve the relocation of the existing Belle Vale Day Nursery resulting in the current building/site becoming surplus to requirements.
The new centre is integral to the implementation of the Second Phase of the City’s Children Centre programme approved by the Executive Board in February 2006 (CHS/06/06). The centre will provide the following core services:
• 53 centre based day care places for children aged 0-4 • Early Education for nursery age children • A Childminder Network • Support for children with SEN or disabilities and their families • Job Centre Plus • Childminder Network • Family Support and Outreach
Although the City Council is the accountable body for the Sure Start Children’s Centre Capital, given that the project forms part of the relocation of the Infants to the Junior site (a single site) funded through the Voluntary Aided Capital Programme (LCVAP), it is proposed to fund the cost of the scheme by way of a grant to the Trustees, subject to an appropriate legal agreement being entered into with the City Council to ensure the City Council’s interests are protected, particularly in relation to the development of the scheme and the capital grant clawback procedures. In this regard discussions have already been held between the City Solicitor and the Archdiocesan solicitor to agree terms.
Subject to the necessary City Council and Sure Start Unit approvals, the current programme anticipates a start on site date during January 2007. Interim Executive Director recommendation: Stuart Smith recommends that:
(a) the City Council acts as the accountable body for the Sure Start Children Centre Capital Grant for the development of the Children’s Centre at Our Lady of the Assumption; (b) subject to the approval of the Sure Start Unit, the City Council issue a capital grant to the Trustees of the Catholic Archdiocese in the sum of £846,624 inclusive of fees and charges financed from £846,624 Sure Start Children’s Centre Capital; (c) the City Council shall enter in to an appropriate legal agreement with the Trustees of the Catholic Archdiocese to protect the City Council’s interest with regards the development of the project, fulfilment of the conditions of the Sure Start capital grants including clawback arrangements in the event that Children’s Centre Services cease to be delivered from the site; (d) approval be given to the re-siting of the LA Belle Vale Day Nursery and for the site to be declared surplus to operational requirements once vacant to be transferred to the Head of Property and Asset Management for disposal; and (e) the Capital Programme be amended accordingly.
Key Decision: Yes
Forward Plan: Yes
Implementation effective from: 15 September 2006
Time-scale for action:
Subject to the necessary City Council approvals and approval by the Sure Start Unit it is anticipated that works will start in January 2007. Final completion of the capital build is anticipated by August 2007. It is anticipated that the Local Authority Belle Vale Day Nursery will close in September 2007.
Reason(s) for Recommendation:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.