Broadgreen Cycling Route (R&T/41)

Approved Executive 1 paper

Executive Board approved this item on Friday 5 January 2007. Below is the council's own wording, with the papers it was decided on.

Item146j

Resolved

Resolved that – (i) authority be granted to the Interim Executive Director (Regeneration)to accept a Sustrans grant totalling £24,000 for the Broadgreen Cycling Route; (ii) on receipt of an offer letter from Sustrans , the City Council’s 2006/2007 Capital Programme be adjusted and the Cycling scheme be amended from £216,000 to £240,000; and (iii) approval be given to commit the expenditure. R&T/46
Word for word from the decision Liverpool published for this meeting. Source: councillors.liverpool.gov.uk

Follow this further

Built from Liverpool's papers

What the report saysPro

Report to Executive Board, 5 pages

Executive summary

Sustrans (a registered charity) are in receipt of a DFT grant (for which they are the Accountable Body), for the national ‘Links to Schools’ programme. They have already made £26k available from their allocation to Liverpool for the Cycling scheme. This amount was added to the 2006/07 Transportation Capital Programme following the approval of a report to the Executive Board.

The purpose of this report is to seek permission for the City Council to accept a second Sustrans Links to Schools grant of £24,000 for the Broadgreen Cycle route.

The grant will enable works to continue along the Broadgreen Cycle Route. Specifically, it will fund improvements to the subway including upgrading the lighting, improving drainage and cleanliness, and providing segregation between cyclists and pedestrians. This will help create a safer and more pleasant environment for walkers and cyclists. The money will also contribute to resurfacing of the path along The Green and provide a segregated cycle/foot way linking Thomas Drive with Broadgreen Road and Broadgreen High School. This will compliment the Traffic calming measures on Thomas Drive, which is currently at the consultation stage, and provide a link with the Broadgreen Cycle Route.

Executive Member/Interim Director recommendation: Cllr Peter Millea/K Turner and Ben Dolan

It is recommended that:

(a) Authority be given to the Interim Executive Director for Regeneration to accept a Sustrans grant totalling £24,000 for the Broadgreen Cycling Route;

(b) On receipt of an offer letter from Sustrans, the City Council’s 2006/2007 Capital Programme be adjusted and the Cycling scheme be amended from £216,000 to £240,000; and (c) Approval be given to commit the expenditure.

Forward Plan/5 days notice/special urgency:

5 days notice

Implementation effective from:

Immediately upon receiving the grant offer letter from Sustrans

Timescale for action:

Funding:

Nov 06 Offer letter accepted Feb/mar 07 Works on site

Project Programme:

Works to start on site on Feb/Mar 07

Reason(s) for Recommendation:

(1) To inform and update Members on the progress of the scheme known as the Broadgreen Cycle Route – The Green

(2) To advise Members of and seek approval for the acceptance of the Sustrans grant and amend the capital programme accordingly.

Alternative options to be considered:

Not accepting the funding would mean that work will not be able to be undertaken to improve the Subway and The Green for pedestrians and cyclists and link up the cycle route at Thomas Drive with Broadgreen High School and Broadgreen Road .

Due to capital funds being used for the traffic calming measures on Thomas Drive and Advanced Stop Lines along Broadgreen Cycle Route these improvements could not be made without the contribution of the Sustrans Links to Schools grant. Consultation:

Ward members will be consulted throughout the scheme design process. Local cycling groups will also be consulted these include:-

Merseyside Cycling Campaign Sustrans Liverpool Cycle Forum

Residents will be consulted on the adjoining traffic calming scheme on Thomas Drive.

Monitoring

Monitoring will be by way of regular progress meetings between Highways Management, 20/20 Liverpool and ELL.

Financial implications

Capital

As detailed in the Executive Summary, Sustrans (a registered charity) are in receipt of a DFT grant (for which they are the Accountable Body), for the national ‘Links to Schools’ programme. They have already made £26k available from their allocation to Liverpool’s Cycling scheme. This amount was added to the 2006/07 Transportation Capital programme following the approval of a report to the Executive Board on 20 October 2006.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Broadgreen Cycling Route (R&T/41)Report 5 pages DownloadRead as text

At this meeting

Whole meeting
145Minutes of the Last MeetingApproved 146aWheeled Bins Lease (RES/37)Approved 146b12 Hardman Street (RES/38)Decided 146c181/185 London Road (RES/39)Decided 146d14 Fraser Street (RES/40)Agreed 146eSite at Okell Drive (RES/41)Agreed 146f40-50 Percy Street, 53-57 Upper Parliament Street and 1-9 Parliament Street (RES/42)Approved 146g40 Whitechapel/33 Williamson Street (RES/43)Approved 146hCorporate Property Database (RES/44)Approved 146iJames Street Interchange (R&T/40)Approved
146jBroadgreen Cycling Route (R&T/41)This decision
146kNeighbourhood Renewal Fund Year 7 (2007/08) Programme (R&T/46)Noted 146lFazakerley Open Air School (R&T/47)Agreed 146mNeighbourhood Regeneration Further Commissioning Exercise (R&T/48)Decided 146nArnot Primary School – Enabling Works (CHS/27)Decided 146oProposed Pupil Admission Arrangements to Liverpool Primary and Secondary Schools in September 2008 (CHS/28)Approved 146pCity Employment Strategy (ED&E/13)Decided 146qHousing Repair Contract: Proposed Contract Extension (NH/25)Approved 146rCityfocus SRB Delivery Plan 2006/07 - Programme Amendments (SI/5)Approved 146sFormer Phythian Community Centre, Hutchinson Walk (RES/46)Agreed 146tOffices Suite A, 5th level, The Podium, City Tower, Old Hall Street (RES/47)On the agenda 147Former Petrol Filling Station, Queens Drive/Moscow Drive - Anfield, Tuebrook and Stoneycroft and Old Swan Neighbourhood CommitteeAgreed 148Vacants Register - Anfield, Tuebrook and Stoneycroft and Old Swan Neighbourhood CommitteeAgreed 149Overview and Scrutiny Select Committee - 5 December 2006Noted 151Exclusion of Press and PublicDecided 152aFinancial Assistance to Businesses (ED&E/14)Approved

More from Liverpool Executive Board

All decisions
MeetingDecisionOutcome
23 Apr 2010 Minutes of the Last MeetingResolved that the minutes of the meeting held on 9 April 2010 be approved as a true record. Approved Open
23 Apr 2010 New Growth Point - Revised Programme of Development (SSC/43)Resolved that - (i) authority be granted for capital and revenue projects as identified as ‘Priority 1’ in Appendix 1... Decided Open
23 Apr 2010 2010/11 Housing Market Renewal Fund (HMRF) (SSC/44)Resolved that - (i) authority be granted for the Executive Director (Regeneration) to accept a Housing Market Renewal... Decided Open
23 Apr 2010 Refresh of Children and Young People's Plan 2010/11 (ESE/41)Resolved that it be recommended to the City Council that the recommendation and views of the Education and Skills Sel... Approved Open
23 Apr 2010 Croxteth Primary New Build School - Final Business Case (ESE/42)Resolved that - (i) in accordance with the decision (Minute No. 50(b)) of the Executive Board of 12 September 2008 th... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies